tv   [untitled]    July 18, 2024 7:00am-7:31am IRST

7:00 am
after the news , we will be at your service with the continuation of the reporter's morning program. in the name of allah, the most merciful, the most merciful. good morning. hello, at the end of this month, the deadline for completing the tax return is sunday , july 31st. the deadline for submitting the tax return for the year 1402 for natural persons is for legal entities and self-employed individuals. according to the announcement of the tax affairs organization, the deadline will not be extended. in order to benefit from legal exemptions, individuals must declare to complete the fire within the specified time.
7:01 am
in any case, the amount of reeds there was very large, and unfortunately, the way to access it was closed there was no report from our colleagues , but currently, 500 hectares of reeds have caught fire and burned , the continuation of the heat wave in the country at the same time as the forecast of the meteorological organization about the stability of the heat at the end of the week and with the aim of management. energy consumption, administration and
7:02 am
banks of six provinces of the country will not have in-person activities today. the minister of energy asked the people to save electricity consumption and said: we have no plan for blackouts. the temperature this week decreased by a few degrees compared to last week. but in some hot cities of the country, the heat is still unbearable it is worn out really very hot, the temperature is very high. the maximum temperature of the cities of khuzestan and shahr. the temperature in dehloran, mehran, somar and in the city of the province reached above 45 degrees today. on average , the temperature of our entire country has increased by about one degree compared to the average of the last 30 years. this trend has also been something during the year, that is, during the last year, we had a temperature increase of about one and a half degrees compared to the long-term average. jan
7:03 am
bosher, bestak, hormozgan province was one of the hottest cities in the south of the country. ghairo karzin and lamar in fars province, kohnouj, jiroft and anbarabad in kerman province and the temperature in iranshahr, delgan and banpur in sistan baluchistan exceeded 45 degrees. now we are reaching the peak of heat. somehow, let's not let the power of your presence diminish . for example, a small child doesn't understand this thing, it's up to the parents to warn them. go to the offices and see . i went to the banks. the offices were in a very small hall . four of them were on. in hot summer days , more electricity is consumed due to the use of cooling systems. and in some cases , the production network to the distribution of electricity consumption is out of balance it is possible that we
7:04 am
reached the peak of 770 and 115 megawatts by july 20. this is an increase of 7 compared to last year . in fact, we do not have anything planned. health experts also warn that people should not be exposed to direct sunlight during the hot hours of the day. use protective hats or light-colored clothes, because the darker it is, the more heat is absorbed, and sometimes they must be hot with themselves. according to weather experts, from the middle of next week to the end of the week, the temperature will rise in most parts of the country. there will be an increase. mohammad ali golkhah , radio and television news agency. clinic doctors in hamedan visited patients for free in the month of muharram with the opinion of treatment. according to the head of mehr shafa clinic, in this project, which is the third year. that is, a visit to a general practitioner
7:05 am
, an ophthalmologist, a dentist, and a sugar and fat test are done for free, and i took a picture of my teeth. i can comment on my knowledge and help people, and with a free examination , i can take a burden off people's shoulders , do them a good favor, and i hope that imam hossein will be pleased with us. it is a good plan, and this plan will make the culture cooperation and cooperation should be implemented in the country, god willing, i will be accepted by them, i hope you were able to do so.
7:06 am
7:07 am
now in different parts of the world, humanity and the people of some countries are being oppressed. the message of karbala is clear. you must rise up against the oppressor whenever you live. this is the message that the followers of imam hussain, peace be upon him , want to convey to the people of jumbla every year by holding the ashura ceremony. the raising of this flag is not limited only to shiites. some of the sunnis are also among
7:08 am
hussain 's fans in this country. hindu sikh religions they also poured flowers on the heads of hosseini mourners and explained more than water and syrup between them. 45,000 imams of babareh and ashurakhana, along with 15,000 special shiite mosques, hosted hosseini mourners on ashura day. hassan abdul maliki , new delhi broadcasting news agency, specialists of a knowledge-based company succeeded in localizing the sensors of smart eye drops . fixing the disadvantages of water cut off during power cut and high energy consumption is one of the advantages of this localization. localization is the main part of smart faucets. previously, if people wanted to buy a faucet, they had to buy an imported faucet. previously , light sensors were used in smart eye faucets, which
7:09 am
made the operation of the faucet and water exit difficult. the technology that was changed to infrared technology with the acquisition of technical knowledge of sensors . sensors do not cause any problems in artificial or natural light, and even faucets can work easily in total darkness or under sunlight. another disadvantage of smart eye faucets is the dependence of water flow on electricity in places where there is no electricity at all. it is automatically activated on the battery, if it works with the battery itself , it can be used intermittently for up to 3 years if it needs to be replaced, the power consumption of 6 eye valves can work easily and compared to external eye valves that are 110 and 220 volts, it consumes much less energy . by installing a piece at
7:10 am
the outlet end of the valve, the water and air are mixed together, so this makes it possible to understand and feel the pressure of the water outlet. the most important purpose of using new technologies in construction irrigation is to save water, which is a factor that companies put knowledge base for new products on the agenda. vahid zakari, iraqi radio and television news agency. thank you very much for your companion . have a nice day. god bless you.
7:11 am
yes, good morning, dear viewers. okay , god willing, dear compatriots who have joined us from this moment, greetings to you, but let me tell you that we have passed the hot days and next week we will have hot days as well. we are in summer and the number of hot days is more than in other seasons. it is year-round and at the same time requires a management in energy consumption, especially electricity . we are water, let's go to the important issue of electricity and us in the studio, we have mr. engineer namazi with
7:12 am
us, the general manager of the technical office of the thermal power company, to talk about the amount of electricity consumption, as well as the ways to reduce consumption and the recommendations they have so that we can reduce consumption so that we do not face blackouts in the future. as we have a warmer month of august and september ahead of us, mr. engineer, good morning. you are very welcome. good morning to you and all dear viewers. good morning. i offer my condolences on the days of mourning. i hope that the mourning of all dear ones will be accepted by god. very well, you said in the news sections that the consumption of electricity this year is a few. he experienced the new step, the last one was 775 megawatts , fortunately with the tact and efforts of our dear colleagues in various areas of the electricity industry, from production, distribution and transmission. blackouts were not given to the subscribers, of course, the role of dear compatriots in consumption management and the help that is given to
7:13 am
the weakness of the electricity network in passing through this pass and at this point is very important. now you mentioned that we did not have any blackouts. they have a series of small outages, of course, the duration of these outages is not long, but we communicate with them as they are also one of their problems. let me tell you about the shutdowns they have and god willing, we will be able to receive your excellency's answer regarding their problems . naturally, the imbalance is different at different hours and on different days, but the number is more than 10,000 megawatts, of course, yes, and what should we do, because after all, a large part of it is domestic, the majority of it is the main part. our first priority is to focus on the consumption period in the summer, in fact, more on the industrial sector
7:14 am
so as not to put pressure on the household sector, but even spending a little bit, dear compatriots, to the extent that it is now the minimum amount requested is usually the same 10% , which is not a large amount for household consumption, maybe with even a single move, sometimes, even for example , an electrical equipment that they want to use , they just need to arrange the time to a non-peak hour. at other times, this will cause us, because we have peak consumption at a certain hour, in another hour, the network is responding to the consumption requirement of 100, which i said reaches its minimum, but at the peak consumption hour, it is important that our consumption is at the time of hajj. which now can be said roughly from 11 noon to 11 pm and what to do from 11 am to 11 pm means the middle of it it is already an hour
7:15 am
south of the country because the cooling sector really puts a lot of pressure on the network. maybe in the summer, the most part that we can focus on is the domestic sector, especially in the southern regions where there are air conditioners that consume a lot. you can focus on the home. instead of several coolers, one bag should be lit, and for lighting purposes, which is usually already known, the same number, if it is managed , i said a large number. this transfer of its own consumption time is a task that is not too impossible, like high-consuming appliances
7:16 am
, it can be done in an hour other than rush hour used, like morning and late night hours now you mentioned you said the southern and southwestern centers of our country , which have much hotter days than the rest of the country, let us go to khorramshahr , my journalist colleague mr. behrani, hello reporter , yes, hello and good morning, i am at your service , dear colleague ms. hajipour and an expert of your program, dear viewers. we are at your service. be healthy , mr. behrani. please refer to the electricity situation in khorramshahr. do you have electricity in the city as well? yes, now , from the calls that people made to me from the past days , we had this power outage in different parts of khoram city, unfortunately, now yesterday, in the village of sarhaniyeh and other regions, as an example, i would like
7:17 am
to point out to you that we had a lack of power in the electricity department of khorram network at two points at the same time. the equipment makes it so that if at some point the electricity in that area faces a pressure drop or a complete blackout , people must wait for the electricity in that area to stabilize, and then go to other areas of the power supply and stabilize the electricity in that area. in khorramshahr city level , as the officials themselves point out, 40 % of the electricity network cables in the city level are still from there are copper cables and only 60% of self-maintained cables from the level of khorramshahr city have been applied to them. for this electricity network, we have the mino section, a city with a significant population in the khorramshahr section. i am talking about you, during these years , there is only one afa office in that city, and one gas office
7:18 am
, but the electricity office and electrical events have not been seen for that city, and... the same thing happened to us last night , we were with these loved ones at the secret ceremonies. when we were next to them, that was the concern of the people, that is, if the electricity in that area and that city is cut off, i will have to wait let the power incidents and the forces responsible for the electrical incidents move from the level of khorramshahr city and come to solve the power outage and solve their problems. the same problem is still in the villages west of karun, that is, we are up to 80 km from that side. from khorramshahr, which is our last village, dim ibn najm village is 80 km , it is a long distance. until now , unfortunately, we still
7:19 am
do not have an electrical incident team that is permanently stationed there. nawazi heard the words of our journalist colleague in khorramshahr and some of the issues and problems that you raise, well, the section is also very serious, what should be done, of course, some of the issues that you mentioned are related to our good colleagues in tawanir, but i am talking about the section. there are many thousands of kilometers of network. naturally , when the equipment that works in the network increases the temperature, the pressure on that equipment, including the transformer and the network , is natural that it is possible for accidents to happen in the network. where the heat in the south is more, pay attention to that part now we ourselves are working in the field of the production department of their maximum capacity, by the way, in the south of your country. in the last few days, i think a clip
7:20 am
has become very widespread on social networks and has gone viral due to the efforts of our colleagues in the same negah ramin, which is next to the city. perhaps in the southern province, there are some engineers today, and you are also saying that you are talking about the engineers today, in the presence of the minister of energy, who will abstract and appreciate the network that in the production sector of the country is now above 98 readiness, that is, it is working at its maximum readiness. in the network and in the same way to my colleague, of course, in production but high consumption and high temperature really show the work as you have already interviewed our colleagues in that program. working in nigah is hard work by nature, and it is really difficult for you to change the temperature there just because your friends have an idea. you can see that the turbine is rotating between 500 and 500 revolutions per minute. now see.
7:21 am
let me see how much it is and then you will point out how much difference there is between the temperature in the province itself and that of your colleagues and engineers in these power plants. now imagine if the ambient temperature is whatever it is, let's assume it is 50 degrees. khuzestan mr. asghari must confirm that is there or not, but let's assume that the temperature of the environment where the colleagues work is 50 degrees celsius , the external environment of the turbine itself, the turbine room is now 20 to 15 20 degrees more. let's say that a unit is working at 1200 degrees celsius and if you turn it off 24 hours later , how much will the temperature drop, but someone has to go
7:22 am
to work in that environment because a unit like new garam, for the sake of having a mental number , assume this is 300 megawatts. for places with a little less consumption, it will cost 300,000 that is, if one unit goes out, 300,000 houses will have to be cut off. now, with one area and one area in these areas, assuming that there is electricity supply , how can you plan for them so that they can be managed so that others can also plan for them, of course. we have one in tehran itself
7:23 am
. i went to one of these shopping complexes by chance a few days ago . they said that it would be cut off after an hour. now the power will be cut for two hours , but i did not inform us of the hour and minute that should be announced. maybe this is if there is a positive point in the story, see when you have a shortage and before are you ready that in the past years when there was dissatisfaction, which is now a bitter memory, we don't want to repeat it, then it was announced to the subscriber, but now it is because the subscriber will not be turned off at all , so it will not be announced at all, that is, it is not supposed to be turned off, but you, the network is in go anywhere in the world as an operator, go as a network operator , sign a contract with the device that owns it , it never expects you to see the equipment in 100 times because it knows the electrical equipment , especially when it is possible for you to load. an area suddenly increases or to any the arrangement of that equipment which
7:24 am
is added to the load network itself at a normal temperature of 50 degrees celsius is self-renewing under pressure , that is, the operating conditions of that unit, maybe that transformer is not designed to work at a temperature of 50 degrees for a month, so when a this particle becomes stable , long-term heat is possible. he should equip the elephant, so to speak, but what i think is important , what people expect, we are also at their service and to all our colleagues, is that it is back to the time of returning to the grid, that is, equipping what power plant, what network, that it will go out for a short time is one of the the nature of work cannot be neglected and cannot be prevented anywhere in the world, not here, but the important thing is that our colleagues try to return to that time, as you say to yourself, is short. when this issue is resolved, it is very important that all our colleagues are trying to, god willing , allow us to go to
7:25 am
ahvaz as soon as possible, god willing. dear and respected guest of the program, hello and polite, mr. farhani , please tell me about the electricity situation in your province. yes i would like to tell you that just as the guest of the program pointed out, we do not have interruptions with the program, but interruptions without the program, well, the number is not few and there are many , the point to point out is that time, and unfortunately we see this time too long, see the interruption when outside the program well, you can't plan, and it becomes difficult for families to travel twice. i know when you have an outage with a plan, for example , you have a small child, you have an elderly person, you have a patient , you can plan and transfer it to a place where no power outage is supposed
7:26 am
to happen, but an outage without a plan. you can't you have to plan and this is difficult in difficult conditions where the temperature sometimes exceeds 50 degrees in an apartment environment where when the electricity is cut off, the water is cut off, the elevator has problems and many other problems arise, and we hope that now this it is certain that some of them are really unavoidable , but some of them can be avoided and the problem solved. an important point is that the doctor himself said that during the definitive solution, we experienced long periods of time in the city of ahvaz , not in the outskirts of ahvaz, but in ahvaz itself . it stops at 3 midnight and lasts until 12:00 noon, which means something like 8-9 hours this is the time to return to the electricity grid, of course, the heat of the heat of khuzestan province. well, you know, this year it started earlier, in the end of june and the beginning of july , about 6 days. before, attention from khuzestan province
7:27 am
was above 50 degrees and this extreme heat in khuzestan province is causing this increase in consumption . i have a tip for you. now, mr. doctor, i definitely know better. a significant part of the province's electricity is supplied, especially by the ramin power plant, which i confirm is not next to khorramshahr. there is ahvaz and this well, the ramin power plant has ended its life, that is, the working life of the equipment, which is determined by the equipment installed in it, maybe 10, 15, 20 years, and the same incident that was widely spread, and we saw the hard working conditions of the hardworking engineers of this power plant. they do that operation in very high heat and humidity. in fact, this power plant has reached the end of its life.
7:28 am
every year, this is completely normal, you see, every year , a large number of buildings are built , commercial centers are built, various industrial units are built in the metropolis of ahvaz, and these are definitely and warm every day. it is increasing day by day and the consumption is increasing. we need our power plant to be updated to increase production and since the network is assumed to be at the level of our city. ahvaz
7:29 am
was a bit different. now in other provinces, they have intermittent power cuts during the day , but in ahvaz, apparently, there are power outages that last longer and are part of it from night to morning . khuzestan who say firstly, nirgar ramin , really enough since last year when they said yes the power plant is worn out and it has been working for many years, the age of the power plant is high, but you can really see the production number of this power plant with a very high power. a good power plant in this period in the province, including the dukohe power plant that was built in the 13th government , is in the circuit of the class f power plant and is being produced, and there are other works that i will not mention
7:30 am
here. but in khuzestan, after all, part of the energy that is injected into the grid is through the hydroelectric power plants that are in the province. maybe now, friends, in a part of the province , the electricity is supplied through this power plant, and in khuzestan, after all, the thermal power plants of khursheed power plant are different types of power plants, the part that can be explained in another hour . because this is continuing, it's hot, it means that in some places, the weather is a bit cooler, it's always like this in all the provinces. now, regardless of the fact that some times of the day, especially in the southern provinces, it's really hot and unseasonable, as i said, even if we assume let's say there is a shortage at that time, it is definitely not the pressure of lack of production in the network, but the power network , especially in the province, is under pressure.