my name is danny fung the asset manager for power enterprise. here today to ask for approval to increase the construction contract cost is and duration contingencies for existing contract pw-009r, the as needed electrical distribution instillation and construction support. on november 8, 2022, by resolution 22-0197, the commission awarreded contract number pw-009r to vip powerline corp. the contract augments the existing power enterprise utility field services staff to provide services to sfpuc customers, response for emergency outage, improve system reliable and connect new customers. shortage of skills and available workers necessitated support from a outside contractor. the original contract amount was $11.5 million and duration was 2 years that started january 13, 2023 and end in january 2025. as of may 8, 2024, $6.17 million has been released which is about 54 percent of the max contract value. staff recommends the commission approve increase to the contract cost contingency by $4.6 million and increase to the contract duration contingency