tv [untitled] March 2, 2023 10:00pm-10:31pm IRST
10:00 pm
[000:00:18;00] before starting the conversation, with the report of my colleagues in the editorial office of sada and sima news agency , the most iranian phase of south pars has been put into operation . phase 14 will be put into operation with the presence of the president. during the second provincial visit of the president to bushehr province
10:01 pm
, the minister of oil spoke about the products of this phase, which is named the most iranian phase of south pars because of 70% of the manufacturing equipment inside it. phase 14 of high-value products will add 400 tomans of sulfur to the country's gas and petrochemical portfolio, and one million tons of lpg and one million tomans of ethane gas for petrochemical units will be produced in this refinery. this year's slogan is the production of employment and knowledge based on knowledge that it is a manifestation of self-sufficiency in the country of independence. this work has been done in south pars phase 14 refinery. it is an authority for
10:02 pm
the country. with the launch of this phase, the case of south pars onshore refineries will be closed, and only the marine development of phase 11 will have 8,500 people left. in construction the 14th phase refinery participated and from today 1100 people will be working in this refinery mohammad hadi hajizadeh south pars radio news agency south pars phase 14 the most iranian refinery in the countries of tauslipouren greetings and greetings hazrat ali, let's start by talking about the refinery itself today, but let's talk about the nature of the refinery, details and its products, so that we can go to more questions and details in the name of allahur rahman rahim
10:03 pm
, members. dear and honorable iran well, as you mentioned, and today in the presence of the president of the republic, this refinery was opened , it is necessary to explain that we have implemented the executive activity and put the phase that includes the offshore part of the sea pipelines and finally the dry test since 2009 in the form of a consortium. with 8 domestic companies that lead this consortium, we started the organization for the development and modernization of iran's industries to isis . and
10:04 pm
continued in 1996 and 1997 to prevent the non-profit from the extraction of the common field of the offshore sector was prioritized, and we completed the 444 wells that cool and dry the 56 million cubic meters per day of khawam gas, and it started working as an operational operation of the onshore refinery from the end of 2017. and today we are witnessing that the executive activities of the present refinery of 9 companies and 98 contractor companies, which were to me secondary works and parties to the contract of our main contractors , being active in this project is one of the economic problems in the future , considering that we are well, something around 70 the percentage
10:05 pm
of manufacturing of this equipment is from domestic manufacturers and many of these cases were happening for the first time in the country, we have turbo compressors for the export of gas to pipelines in this refinery completely localized from the phone control system for the first time and finally toga mapna company which is very productive and there is also an international one, let's do it in the sky. the whole control system of this refinery is the mastermind and i have control over all the devices of this 171 refinery, which is about 280 times the size of a football field, from one room to control all the logic and software and software devices. and hardware was done by a knowledge-based company, including all rotating equipment of course, the pumps of this refinery were built before, but
10:06 pm
it was used for the first time in this refinery. we had done part of the equipment of this university to be supplied from foreign manufacturers, despite the fact that the equipment and pumps were delivered to us now or to those who didn't deliver, whose task is clear, those who had delivered , complained about providing assembly plans, and this is a puzzle and using knowledge-based companies and experts with experience. and their arrangement it was a very complicated job, so let me tell you that we used 70% of the equipment from domestic manufacturers, but 100% of this equipment from the time of installation, pre-commissioning and commissioning was completely done by domestic companies
10:07 pm
, even a foreign supervisor who was under their contract. and being required to supervise the process of launching the moon, and today we are happy that we were able to localize this knowledge, a great work that we did , we started reverse engineering for this 30% of the equipment that we had provided by foreign manufacturers in the form of spare parts to knowledge-based companies. several knowledge-based companies handed over the entire construction process. he came and made a map . god willing, it will be done with reverse engineering. in the future , we will witness the construction inside them.
10:08 pm
in both spheres, mr. shariati, i wish you greetings and welcome again, your excellency , do you think how much this phase will help to provide sustainable energy and energy security in the country, in the name of allah, the most merciful, the most merciful, at your service and all the dear viewers. i would like to say that i must first thank the respected government, especially the ministry of petroleum and the respected minister of petroleum, for their efforts to complete the remaining projects of the past , as you mentioned , the completion of this work has been delayed for almost 12 years, and the refinery capacity of the country in the open field, which if 10 years old, should be completed. let's take into account that the $3 billion series is now a forecast, we have $30 billion of the unprofitability of this 10-year humiliation, and a few years have passed and the country was not in a good year.
10:09 pm
that passed, we experienced to some extent that if the effort let's not finish the production, then consumption management may have problems. fortunately, the government has probably made a good investment. i must mention that we have added a refinery capacity. still , new production capacity has been added from our reservoirs, and it should definitely be a priority project of the ministry in the future. oil and gas company, but what happened is this 50 million cubic meters per day, which helps to refine more of those by-products and the export value that we used to use the processing capacity, perhaps to some extent, from the empty space of its refinery capacity, using its capacity free can we use it with more capacity to produce cultural
10:10 pm
products , especially? the next point is that we must talk about torch gas, which was like honey today. they helped the development of different phases and tolerated the destructive effects in this case. for the country's economy, we should especially appreciate them , and the people of the region are one of these discussions of gratitude that we work for their environment . fortunately, this year for first time and for gases mashaal, we thought and said, how many years will this take? it was already followed, and especially in the last ten years, because of this incident, we will lose around 10 thousand billion tomans at the end of next year, if the phases of mashaal gas extraction and processing are not followed .
10:11 pm
500 tomans per cubic meter has been approved in this year's budget, which will help from the ministry of petroleum's internal resources to address the same problems . in the parliament from bahman zavi, the country's natural gas sector and electricity sector and the country's fuel supply is one of the topics that was emphasized that, in addition to the discussion of the country's production and the increase of our refinery capacity, we must definitely go towards consumption management and practically to virtual refineries. in the field of natrazi, open and complete the value chain, because no matter how much we save, we can develop new petrochemicals with added value and earn high income, and my man, i swear , he deals with the government's plans regarding the role of the field's budget, but the communication has been established with
10:12 pm
mr. mohammad hossein mutajli pars oil and gas company commercials, hello, good time, greetings, politeness and respect, dear mr. aziz and colleagues of channel one, mr. dr. malik shariati, honorable representative of the islamic council, greetings , dear viewers of channel one, mr. we are at your service by god's strength. regarding the construction mechanism, please explain to the viewers how many companies and how many investors were involved in the construction of the refinery and how much this operation of the refinery will benefit the country and how much employment it will create
10:13 pm
. as main contractors this project was considered the king of domestic construction, the investment of the king was considered 14, it can be said that 7 billion dollars were invested for the dry refinery, 150 million man hours of work have been done in the refinery so far , a series of other units must be completed .
10:14 pm
3,500 people have been employed in the course during this period. thank you very much for your explanations, ceo of pars oil and gas company . these conditions the embargo and the problems that existed, there must have been obstacles in this path , explain this dish to the viewers, how this success was made with these obstacles at the order of which king, now, as you rightly pointed out, maybe we can look at these previous cases and the challenges that came with it. we were faced with the issue of bad faith of western companies, now due to the sanctions imposed in our dear country, we should also add that we were on the side of the builders, whom we should
10:15 pm
have trusted, and for the first time , we handed over some of these equipments and facilities to them. you can with a sour gas that accompanies we are in favor of a large amount of revolution to the carbon dioxide sulfur citadel, which, god forbid, if we have the smallest leak, the term is inhaling and not exhaling, and regardless of whether this equipment is made inside or outside, it must completely meet the safety standards. to do it and pass the relevant tests, mr. seifi, we had two options, either we had to wait for the contracts that the contractors had closed before to be reactivated in good conditions, or we had to continue on this path, but we definitely couldn't
10:16 pm
wait and look for these domestic companies. we went we made a call, we sat down together, the employer supported us, and the manufacturers gave us heart to heart, believe me, many times during these years , they would take the equipment, install it, take it to the service, after it would find a problem, it would be sent back to these factories again and again. and it happened many times, but we, as a group of employers, supported the domestic manufacturers , we provided them with this permission, this space for you , which is trying with the confidence of the brand to reach the desired result, this happened, the machines of the world took over that the result of trusting young people the internal specialist was such a success for the country and we also had a control machine that
10:17 pm
was really placed in the path of sour gas for the first time in this refinery. we tried it at one point with sweet gas, but if we failed and there is a problem with this function , it should be clear here that god forbid we should not harm each other and the loved ones who work there, but anyway, this point will add to the time of our project . the interesting thing is that we the first line of sweetening of the four men that we put into the production circuit, these times were very long, but as soon as our first line entered the production circuit on january 27 last year, within a period of 11 months, we made 11 kurds, which is much higher than the previous 12 refineries .
10:18 pm
short about in a shorter time, nearly 50% of that time, the pre-commissioning operation and the commissioning of the first actions and records that happened in phase 14 of south pars , and we gained very good knowledge that i think is definitely worth the repairs that we incurred. mr. doctor, not all success will be achieved except for the support and support that the members of the parliament with their own laws think they have for this plan, now the energy commission of the parliament specifically supports the plans of the ministry of oil, and especially in the budget of 1401, what is your plan to realize this important yes, before i present this point, i would like to point out that by referring to the sanctions , we were really facing a self-sanction, now in this very typical phase in the triangle of game 11, which i mentioned, there are some parts left and it should be completed with the project.
10:19 pm
we took care of it from an iranian company at one point leaving it for the westerners, they came and left it half-finished and gently put my hand on the walnut shell. leaving with years later, you will return to the iranian company . it will be done for people, maybe high or low , the 11th possibility of exploitation. getting this university is a very symbol to the engineers of the chemical engineering of the year. in front of this gas refinery, the presence of trust in people who have high intelligence and ability to work, spend their time and the same workers who are working there, did he really appreciate them? let's help let's leave the work completely to the knowledge transfer to be done during the work of our own scientists. later, see what
10:20 pm
they have done. when i have the meeting tonight , there are different models in the contracts, but i will only look at a few specific western companies and not to do this. we are talking about the phases of my own country's project. we are talking about my own project. the point that you mentioned in the parliament, fortunately, this year, the energy commission paid special attention to this . i would like to thank my colleagues very much. from the middle of sha'ban, we should send the signs of the guard to the people. there were very good competitions , in addition to helping the government's own plans , for example , the government had invested money to complete the western ethylene line, despite
10:21 pm
the problems that existed in the country's sights. it was approved that these petrochemical projects should not be carried out due to 24 problems, approximately 190 thousand billion tomans in addition to the current budgets of our country, from the internal resources of the ministry of oil, we allocated 95 thousand billion tomans for the area of consumption optimization at the same time investment in the field of capital the investment of ship economy is one thousand billion tomans, the gateway to optimize the consumption of renewable energy separately in naft abadan, in the field of oil and gas , there was almost 190 thousand billion tomans allocated, which if 95 happened for the first time, we finished the month and optimization of 10 thousand billion tomans for car gas storage, there is a possibility that we will go below 2% and, god willing
10:22 pm
, we will compensate for 15% for gas storage. aside we asked the senior managers of the ministry of crude oil how much to produce, how much to consume, how much to transfer , where is nadir, do we have isis in the middle of two and a half percent of it at the moment, we have almost 1 billion euros for this issue, we need to remove 50 thousand tons , we have allocated 8 thousand billion tomans for this issue this year. and it is very important to eliminate smuggling, to reform the country's fuel network, to reform financial relations , to create a price increase in the final product, there should be a disciplinary work, a sign and smuggling of fuel for the country's power plant is also considered a very important point. completion of the refinery the seal of the persian gulf, which will prevent our discontent for the coming years, in the field of gasoline
10:23 pm
, 500 million euros was allocated to oil and condensate. in total, these approvals are collections that help the parliament , and the government is definitely speeding up to compensate for the lag. some things need to be done faster and with more time. i hope that what happens will get a good budget for the people. the energy sector was one of their most active years . and establish a higher speed mr mohammad ziyad group of energy companies of mustafafan foundation, who is one of the eight members
10:24 pm
of the consortium of investors in phase 14 of south pars , mr. zir. in fact, one of the eight members of hossein investor consortium, let's talk about how much we invested, what actions he took, and what plans we have on the agenda . always, as the president of south pars, the opening of the 14th phase of the year of knowledge-based production and job creation, and well, mustafafan foundation is serious about it. in line with helping mater governments and also meeting the people's needs
10:25 pm
in the field of energy were the group of energy companies of the foundation company , which were involved in the construction of the south pars refinery phase 14 . and the noble iranian who was in this university had 110 million contracts and the respected employer of the oil and gas company has worked as a servant in the padri complex of the refinery and it can be said that the high and what percentage of the construction of the installation of all process units is the king, including
10:26 pm
sweetening and building information retrieval mr. ziad's collection of such parts is very short, the opportunity is very short, how much did he use the knowledge-based companies. in this way, the knowledge-based companies played a role in the development of the refinery, what is the gate installation lesson 12, internal construction and the first construction, and our needs , the energy companies of the veterans' foundation in the year 1399 billion tomans, our contract is with danesh banyan health company and god willing, next year ceo of mostafan foundation energy companies group, we have 30 minutes of time, one minute at your service, one minute at the service of the doctor , please. that
10:27 pm
to be clear, this contract was signed in the form of an ip transfer between the 8 members of the consortium and its resources are from the national development fund and the resources are at the disposal of the national iranian oil company, and in fact our investor is the national development fund and the contractors played a role in this matter. i would like to congratulate the dear people of our country on the grand opening of this mega project, from the people of bushehr province, kangan city, that all these hardships and problems caused by a big project should be tolerated well. and within 30 seconds, the latest information about the development of the field i beg the viewers, because i am not the subject of this program, i am a manifest
10:28 pm
engineer, to listen to your explanation that these big projects should be given a special role for the people and people's capital in the field of oil refineries and petro-refinery. with us, we have a law. now, the field of petroleum refineries has a very important law, for example, it has assigned a minimum of 30% of the capital and transfer it to the people through the stock exchange. in fact , the shares of the projects with the public report of the public joint-stock companies are very good and excellent projects, very good to share with the people. in these profit cancer projects it is very good and projects like these will be automated in the future if you can make the people honorable , the serums that are available to the people in the form of mobile cash and even the funds are only riyals, the same arab capital is available to the people if the government itself is a small part
10:29 pm
the percentage of 20% is the same as that of the martyred king in 12 years , gasoline and all these things should work. in these projects, do a new project and let's model and institutionalize this model in the country's economy . the country's macroeconomics in the field of large road projects we have to follow this model. from here, we will want future projects, especially in de-proprietization, to complete the phases and take place, so don't think that the liquidity management of the people's economy will be formed. thank you, mr. tusalipour, and you, mr. dr. and all those who joined us on video and by phone and thank you for joining us with
10:30 pm
a special news interview in the name of god, salam, have a good night, and in the meaning and glory of football tonight, you are welcome. let's start with some news about iran's football, the cancellation of iran's friendly match. and iraq, the head of the iraqi federation in an interview with one of the media of this country announced the cancellation of the friendly match with iran's national football team and said that