tv [untitled] January 12, 2012 10:01am-10:31am PST
10:01 am
we would like to have everything at the same time. that makes more sense. just briefly, the phase one, we have now been awarded work to 50% of that. we have committed 635 million. others will be followed shortly. work done to date has been just over 400 million. this gives you an idea of where we are. the bus storage project should be ready to go out to bid next year, and we will have construction finished by 2014. the utility relocation work is complete. the transit center building, we
10:02 am
will do a series of design and it awards during this coming year. all design will be finished. the below grade structure contract will be awarded next year. the glazing is a long time because you cannot build it all quickly. you need a lot of markups. that is not critical at this stage. that is due to be erected and finished early to the middle of 2017. the superstructure, which will be bid out will have a lot of steel work, and that is the next one after the below great
10:03 am
concrete work. the building and finish is the last piece of it. the bus construction will be phased in to go with it so we can have access to the building with opening everything towards the end of 2017 to usable terminal. the tpx design will be going very slowly in 2012. we have presently scheduled funding to start final design in 2013 to start going into construction with a schedule to in fact have reaail operations y 2020. that would be caltrans and or amtrak. so the plan for 2012, the real
10:04 am
work is in fact moving into finishing all design work so there will be no more design work after 2012. the construction side is about shoring up the excavation work, and we will be working through the completion of the excavation one by one. some starting at the west end and working from west to east. and we expect to finish one and two, including excavation and how that was retrieved. the terminal in 2012 will continue to be maintained and operated in the same successful
10:05 am
way. the bus and storage facility, we will finish the design and our schedule to complete that final review in november. getting ready to bid the project out in 2013. real-estate acquisition, we will be working to complete an assembly on block 5, which is behind 201 mission to make that a single parcel. the new bus ramps, the design is we will go through the basis that we normally have for approval. the final review by october of 2012. we can put that out to bid in 2013. the transit center building will have all the design work completed with the building construction documents.
10:06 am
we will put off until 2013 certain specialists packages like that i t communication, it come security signaling work, because these do not to be -- not need to be designed now and then find new methods. we will complete the supply system and will complete all private utility relocations so we can finish wall. the project will be as-needed services during this year, and we will be focusing on the systems elements for the rails so we have a the same system. it is the same consultants.
10:07 am
we will continue to work with all of our partners and real business as the year goes by -- in rail business as the year goes by. the contract activity for this year, we will have the substructure, which is the next big contract, around 80 million, intended to be awarded mid-year 2012. we will have another one of the small contracts for pedestrians sidewalks in july. the above-grade project will probably be in november. this will be the structural steel work. we will obviously award the construction management services with the bus storage in march or april.
10:08 am
that completes our plan. i would like to hand it over. supervisor kim: thank you. >> good morning, directors. i am legislative affairs and community outreach manager. i will be presenting the community are reached portion of this year's report. we have two primary goals. number one, we want to keep the public and our neighbors around the site who live and work around the site informed of our construction activities, in particular any changes that will impact tropical rafficl flow ory to day activities. we want to let them know about the milestones we are reaching. we have five regularly- scheduled mechanisms in place. with a monthly community are
10:09 am
reached meeting -- outreach meeting that anyone from the public can attend. we advertised that on our web site and any of our materials. they are very well attended. we now regular get seven dozen people attending the meetings filling up the large conference room. it is mostly people who are interested in the progress of the project. people are curious about the construction activity. and of course what the transit downtown will mean for the city. we also have a citizens advisory committee that meets every month that is made up of representatives that are going to be utilizing the new transit center.
10:10 am
we are currently soliciting applications for new members on that committee. we have a 24 hour hot line that anyone can call at any time if they have a question or concern about anything happening at that moment on the site. a member of our construction team is there to respond. if the response is insufficient, then we are able to respond the next day. we also do a 10-day construction outlook that anyone can sign up through our web site. this talks they today about the construction activities and also talks about any changes to traffic flow, detours inside what closures. we have implemented a new quarterly newsletter here yet we want to highlight the progress we are making, specifically in the form of major milestones.
10:11 am
we are sending this to all of our supporters and the federal and state agencies we work with, neighbors around the site. all of you are on the list what we highlighted in that it was the completion of the demolition work. 55,000 hours of labor without any accidents or injuries. that is something we're very proud of. in addition to the regular mechanisms we have in place, we work with the consultants to be generating media coverage that will raise awareness about what the new transit center will mean that for our city, region, state. also about the milestones that we have reached. we also want to take the media opportunities to talk about what the media project will eventually be.
10:12 am
the archaeology exhibit that opened in december got substantial media coverage. we had a story in "the chronicle." we had a story that was picked up internationally. it was picked up in "the huffington post." just to quickly highlight some of the milestones we emphasized in the community are reached this year, we mentioned archaeology, the completion of the above grade demolition work, the extensive utility relocation that was completed in 2011. and we also had an event with the mayor. we also talked about the progress made on the transit center. in 2012 we will continue all of
10:13 am
our our reach to our neighbors. we want them to be aware of things like subterranean the demolition work that will continue that will create vibrations. we want neighbors to know that is coming. we will continue our monthly at reach meetings, citizen advisory meetings. we will continue to work on our media out reach. we take very seriously their responsibility that we have to educate the public about everything the new transit center will be, the fact that it will be a national model for transit-oriented development. the ability to bring an amtrak eventually, bringing in high- speed rail when it is ready.
10:14 am
and the buses that will serve 35,000 each day. we want to make sure the public is aware with that, i will turn things over to sarah, our cfo. >> good morning, directors. sarah gillatie. i know we have time constraints, so if your questions afterwards, i will be happy to answer them we continue to focus on the numbers since the inception of our project. we have awarded nearly $208 million in contracts. today we have paid out over 100 million. 20% of our prime contractors are certified small businesses.
10:15 am
over half of our subcontractors are small businesses. the next slide shows our goals and payments for each fiscal year since we started the program. you can see the payment number has continued to go up each year, as well as in most years our awarded percentage is going up. we will continue to put a lot of effort in this area, contractor meetings to give networking opportunities to meet with prime. we will continue to set aside work as is appropriate. and moving on to funding, our funding accomplishments and 2011, we received three grants for state and federal securities
10:16 am
funds they are passing through for us. week received a rail line relocation grant. -- we received a rail line relocation grant. we have announced we will receive one. 21.24 grant for environmental work. >> could you go over the block 6/7 proposal with the circumstance that redevelopment cannot pay and to read continue. >> it might be most appropriate for mike to come up, but i know the plan is to transfer them over to tpga. they would take over negotiations and contracts. >> we were paying the
10:17 am
redevelopment agency for staff time to renegotiate the development agreements on the state-owned parcel, with the exception of a parcel t and f. where we are now is mike advised of the winning bidders to hang in there while the city creates a successor entity. it will take action. the idea is for transbay authority to continue the work that redevelop it was doing. we would negotiate with the read developer of block 6 and 7. we would then put up the bids for the subsequent parts. and supervisor kim: my understanding is we would not be able to bond against the tax agreement for block 6 and 7. i was wondering -- >> we were not going to bond
10:18 am
for block 6 and 7. affordable housing will be the issue. it is going to depend on whether the director finances at the state level grants us money we need to do affordable housing, otherwise it could potentially be a market-only property. that is not in our hands. that is in the state's hand at this point in time. supervisor kim: ok, we will talk later about that. to go we're following the mandate. we would love to see the affordable housing, but without the money that the redevelopment agency was using to help fund it, that is an issue. that will require the help of the city to get the state to help us with that. it is not just us, is all of the projects in the city. >> good morning. mike risso from the soon to be
10:19 am
eliminated redevelopment agency. there has been a bill introduced in the legislature sponsored by gerald steinberg that will designate all of the low and moderate income housing fund as unenforceable obligation, which would mean there would be at least a large portion of the funds available for the successor entity. for that reason, i think there is still a lot of discussion going on about whether or not it makes sense to facilitate the development we and talking about to transfer the parcels. we're still looking at that. this happened very quickly, and i do not think we know exactly what the ultimate vehicle will be to get the persalts developed. we do know the city will control the parcels and the tax increment will flow to the
10:20 am
transit center, but the exact process we have not figured out yet. in terms of housing, i think the bill that has been introduced in the legislature would be a big step towards protecting the affordable housing funds, but it would not be the whole answer. >> as i understand it, part of the central stated intent of the governor is to eliminate funding for affordable housing. certainly i spent months of 2011 as various part of coalitions trying to stop from happening what happened, and it was communicated in no uncertain terms that eliminating funding was not an unintended consequence, it was the goal. i would be very surprised if the
10:21 am
governor signs the bill. that said, i have been as surprised allot in the past year. i would think we should not count on that. and but i guess it is not the is not tpga to figure this out. i do not know what we do. supervisor kim: thank you. >>director ortiz: i hope that my people are showing up to support there'll steinbedarrel steinbe'. we are definitely supporting it.
10:22 am
>> the slide show at the funding plan for phase one has remained stable. the have not been any change in for the funding commitments at this time. in we understand that tighter for applications will be due in 2012. we will pursue funding for either bus storage or bus ramps under that program. there are two more state security grants that would pass through to us. we just submitted a grant application of the federal highway transportation community and that a highway program. sockewe have our applications id
10:23 am
we will keep you posted on the award when it comes out. and with that, i will turn it over to brian to wrap up. >> one slide. what i hope to tell you and expect to tell you this time next year, all the relocation work will be finished over and closed out. we will breathe a sigh of relief frankly. zone 1 into will be all the way to the bottom and in storing the microfibrils to hold the concrete blocks because we're below water level. the first and fremont streets will be complete.
10:24 am
some three and four, which is basically from first street to deal streetbealle stretet, we we finished on that. we will have the below-grade structure and above-grade structure packages awarded. and we will have the bus storage in the bus clamp bridge construction contracts out to bid this time next year. any questions? >> to questions. -- two questions. if i am putting together all the different slides in terms of time winds, it looks like the building design will be at 100 percent signed this march. it looks like building construction as our starting out
10:25 am
-- is not starting for a couple of years. and basically because we are doing a cmgc, we have the ability to award an individual packages rather than one huge one. in some of them may not start work for a year or so, but there is a long time of fabrication that especially steel work. we need to get that particular package out. we want to make quite certain by this time next year we have bid and received packages. it is not just an estimate, now we know where we are. >> thanks. the other larger point, looking
10:26 am
at the funding plan and seeing the 2.6 needed for phase 2 that we still have 1.9 or nearly 2 billion of tbd and given the larger dynamics with regard to high-speed rail, i am wondering if we should have a broader conversation here about what is happening with high-speed rail and what the impacts are for this project, what the more and that the outlook for phase 2 funding and how these things relate? just like the redevelopment dissolution was the internal inject that change our assessment if high-speed rail were not to continue as planned, that would change the context and assumptions under which the project is moving forward. >> with all due respect, that
10:27 am
would not change the assumption. senator feinstein is working very hard to preserve the 3 billion that the federal government awarded to the state of california. she, along with nancy pelosi and senator feinstein are working closely with the governor at making sure that happens. having said that, the high-speed rail project is a very long- term project. high-speed authority was first looking to target the central valley as the initial segment. they are still undergoing environmental review on all components. that is when to take some time. and -- going to take some time our project is designed under state and local law to accommodate a future extension
10:28 am
to the east bay. it is also designed to accommodate and track to southern california. -- amtrak to southern california. as you know this is only 8 billion or 9 billion for the entire state of california. 950 million was going to other projects of that connect light speed rail. we were not going to get the money we needed from that pot of money. the 400 billion we a gone from the federal government is committed to the project. we have contracts. and the real money is we are looking at to fund the cities to ouare u starts. we have talked about being next
10:29 am
in line to qualify for new start. it will take a collective approach in the support of the city and county of san francisco to help us in those efforts, because as you know, to build a new rail extension you need a new start. that is the only large funding pot you can go to. there are numerous states where the city has more than one that new start in the pipeline. so we are looking at new starts now actively as a source. we are exploring a number of other options which will not materialize until after the presidential election other categories such as funding for intermodal facilities across the
10:30 am
country. in order to raise the 2 billion, and the mayor has been very supportive that he is going to work very closely to help fund the hon -- fund. he is been very supportive. now the central subway will beginning the money soon. i think the next logical project would be the real extension. -- rail extension. we are mandated by as they and local law to do that. -- by stae and local law to do that. director ortiz: we are designing that with high-speed in mind, correct? if for some reason the high- speed rail