Skip to main content

tv   [untitled]    August 27, 2013 12:30am-1:01am PDT

12:30 am
boarder project delivery. we've been getting many analyze about more delay. it doesn't serve our city well, when they have the leadership around the b r t when those projects - they just drag on and on and we sfend more money on the process. it's been a decade and it's completely unacceptable. my question is this is a nice power point presentation why should we - and i guess it states we're going to trim two years off the delivery why should we have confidence this is going to actually happen he
12:31 am
in terms of that shorter deliver process. given the challenges that mta has had and in delivering the projects in a time effective way why should we be confident this is real. that's a question to staff. through the chair >> that's an excellent quo. basically you're saying why should you trust us >> let's be clear this isn't about the mta this is a boarder issue why should i trust the process in general. this is not a hit or criticism directed at the city staff >> if you feel compelled to stand up.
12:32 am
but back to this particular project we also at that time, point have had the ability to absorb some of the lessons and we have some understanding of the rapid bus transit so we you shouldn't have to have the same discussions oh, again. another part that will go towards the credibility this is not a rocket scientist case. we can start to get some of the improvements only the ground and that will build more conversations we can deliver and tim can speak to i know there was a presentation speaking to the mayor's office that they're under talking to deliver the
12:33 am
larger and small projects and a director for the strategic planning. i think supervisor wiener and other directors you've made the point very clear. we're acutely aware of this issue. we're looking at ways to improve the project delivery. but you're correct the environmental analysis has taken lee a long time. there was a decision made that should be noted a few years back to not do the improvements so we can get the larger scale projects out the door. now in behind sight we need to have the incremental improvements to bring in
12:34 am
incremental improvements and at the same time deliver our projects better. there's a very rich process in san francisco. and working with that rich process has had it's challenges. the more it is up consonant o front we'll get a better picture. but i want to stress we're working very closely with the transportation authority to make the best way forward. we believe we have a process to improve the project gary. i'm happy to go more into detail after the presentation >> chairman. how - and i know that the mta wants to improve the project timelines. it's not just a challenge with
12:35 am
the larger projects but the smaller ones. it's sometimes very brain damaging to move projects forward >> yeah. >> and that's for small not hard ones that have a lot of community support without a lot of controversy. so in terms of confident levels that once the mta finishes the analysis this is a realistic timeline. given the time it will take another 5 years to deliver the project is too long but but why should we be confident. and in the context the mta was prepared to force that project to be side lanes and it wouldn't
12:36 am
be beneficial and mta was barreling in that districts and because of some creativity thinking we were able to come up with a resolution for the center lanes. given 3 history and this history why should we believe it will be deliverable >> we see it differently. we work very closely to come up with the center lane proposal and to speed it up. while it wouldn't get you the full beneficiary it will get i incremental improvements. the community pressures that will reduce the time benefits we came up with the proposal
12:37 am
together and i actually that is not my recollection of why they were pushing for the side lanes it was for some operational reasons so my recollection is different >> we'll let that one pass. we feel more confident because we've had increased the training and set aside project managers to take on the side street proochdz. we have the project that was a rail project but we made it a complete street project we improved the bicycle lanes as well as and that came in under budget. when we put our heads together being very clear about the scope and schedule and actually having the budget to deliver we can deliver on time but when the
12:38 am
expectations are not clear we have those discussions oh. i can list you a dozen projects from a simple baseball bat to other similar projects >> i'll stoney hope that mta is moving in a better direction in terms of project delivery. it's just been a real challenge on a love issues. and i won't get into the project the church and mta refuted to correct it >> i want to join the colleagues. i like many of us in this body have been a long time supporter
12:39 am
but it's embarrassing how we're not able to deliver the process on time and we shouldn't have us hold up the projects to facilitate the meetings we've heard over the past week. i understand that finally mta and go others are getting together and how they can deliver their projects better. why should we not continue this item to really understand what exactly you guys are going together but from our prospective this is work that should have happened out our intervention and i have concerns if we're not watching this will continue so explain to us and assure us in the coming weeks that this will be dealt with in
12:40 am
a better way and what kind of deliveryables will we receive to make sure our trains are running on time >> yeah. it maybe that some of this b will come out in the presentation. but your first question was why not defer this until the end meeting. the project will keep moving by the other way it is slowing down the consultant work on the environmental won't sped up is the process. i think you're right about watching this closely. one of the elements we had is making sure we do regular meetings to the mta board on this project.
12:41 am
additional at sometime we should have a meeting >> i think that's a great idea. >> very good commissioner campos. >> actually, i wanted to thank president chiu to help to pull together the mta with the ta and this process with the single team approach is the right one to move projects forward more speedily in addition to a a lot of the other sessions that will come up in the presentation. my understanding of the b r t whatever it's at its sometimes much more simple than the gary boulevard b r t with the tunldz. i know that a lot of the planning into the environmental
12:42 am
analysis is much more complex. i think it's my understanding that this funding for the engineering group and the xhauch design is in and out out of the budget it's only being phased in itself a phased approach so it's not an additional amount of money but it's important for the complexity like the project gary boulevard the tunlz that are divided differently. i urge the colleagues to think about this. that is a phased funding system. there's great things going on i'm happy we're discussing that. but i think detailing this would be harmful and we need the environmental report done and the approach that the
12:43 am
transportation staff and i thank the gentleman for being here this will help to engage the neighborhoods to be a part of the process and i'm for that process as well >> i think the idea to join mta and ta meeting to get the projects moving more quickly and i'll be very brief. i think that the issues that are raised are important but i think they go beyond this individual project. the issue of coordination and project delivery is something else we've been discussing and so i think that if we're going to start talking about that we should have a larger discussion about project delivery period. i think with respect to this project this project has moved
12:44 am
forward in the right direction. i feel and understand the frustration by it's a frustration that i think should be focused on the larger issue of the overall transportation agencies within the city. i think that the joint meeting make sense and i actually also think that having a discussion about sort of who owners the project and who is ultimately responsible if something goes wrong should be a part of the discussion because sometimes you, have too many cooks in the kitchen but i don't see any delays. thank you very much. commissioner weaning you have any other comments
12:45 am
>> i appreciate the work that's gone on over the past two weeks to get this back on track in terms of the timing. my confident level is not high i will support this today. i don't want to cut off our notices despite our faces and denying the funding or detailing it as frustrating as it is we're in the phase of this project detailing it will not help the project. but i want like the better market street plan i think we do need to as a board start exercising some very hands on consistent oversight and regular report backs in terms of what progress has been made are we on
12:46 am
track? is the timeline holding? i think we're going to have to see that over the next 6 months. but i will support the time overview item today >> i'm glad we want the project to move. so i think we're ready for you and a well, thank you very much for that set up oar i'm the director for the capital projects. i participated in the meeting with director reiskin and the san francisco municipal transportation agency. i'm going to talk about the recommitment and management efforts that the two agencies intend to take. i have with me the mta project manager and should there be any technical questions david will
12:47 am
be happy to answer those and, of course, we have wretched e representatives from mta here today to answer additional questions. just by way of set up weighing we'll menace the gary corridor. more than 050 thousand corridor riders a day are identified by mta. it's a prop k cased specifically identified within our expenditure plan. the document began work identifying the 3 projects. since then and part of the reason for the growing complexity of the project is a sort of a variation on alternative 3 the center lane bus rapid transit project. this involves a consolidated
12:48 am
approach that used both the limited and local service essentially operating the same facility. the goals that have come out of the meeting with mta and reflecting the urgency that the commissioners have communicated to us is to certify the document and have a full transmitted service by 2018. the key, of course, is how do we get there. so where what are the means to achieving those goals. we think one of the most useful is to take vague of the federal map legislation 3 will help us to identify the local identification earlier and keep
12:49 am
it within the document. a significant amount of effort was exerted in the vanessa document after the circulation and incorporating that into the final document we can save a significant amount of time. we think the project will allow early deployment of side running improvements in the inner gary and those could be deployed that eventually we'll have the service provided peril. mta and ta are embracing the idea so the people can see the improvements. and mta is very focused on the low cost improvements
12:50 am
immediately fund the certification of the environmental document. in fact, mta has announced the goals by mid 2014 in the mid gary area. looking at oiflg a locally identified alternative in the document there are a couple of options that we think have the potential of becoming the alternative. and their depektd here. it would include the option to provide a filed at fillmore in order to reconnect the community that maybe as much of a land use and community issue as a
12:51 am
transportation issue by those optioned will allow this to be done. side lynn b r t would be provided and the center lane b r t to 22 avenue and a consolidated bus service further to the west. other maples of accelerating deliver including looking at number one traditionally means of delivering the project. maria mentioned the designed risk and we've done that on the vanessa project we we can the same thing can be done on gary. we're confident we know what the alternative is and that's the time to begin van the work.
12:52 am
we're looking at the non traditional means of construction. the construction management guaranteed management these are variations of construction methods that are generally proven to speed project delivery and they tend to be a little bit better of job allocation. we're also looking at strengthening our project management approach. we're moving forward with integrating the authority into a single team. i will say that the representative and team members from the two agencies meet twice a week on the project and we're seeing the people who are participating in the project more and more becoming a chief
12:53 am
team. one of my falsifies is when we reach a joint decision to try to move on. the same thing in project delivery you only make the decision once there's a tendency to try to recycle back and that's a speed killer. as maria suggested we're looking at to have the two agency require and receive a periodic updates that look at scheduled compliance and budget compliance. as part of the formation of looking at the procedures as disputes occur they don't fetter at the staff level and remain unsolved. and that the form escalation has
12:54 am
form deadlines so the project can move forward. and lastly we're working with mta to streamline the hand off once the environmental document is ready to go further. and that concludes the presentation. i'll be happy to answer any other questions >> colleagues any comments or questions? >>. okay. thank you week go on to public comment on this item or those items. >> good morning. i'm jackie sax i'm a member of the citizens advisory committee i've been involved with the item open gary
12:55 am
boulevard since 1986 and back then i was appointed to the gary transit task force to look at the feasibility of the gary light rail system and this sort of thing but it was put in the sales tax passage. the gary light rail project is the only project that was grandfathered. and the gary rapid transit project is supposed to be rail ready. also you have to remember that it's a central sub by the way, there's a stop at the union square and there's a spur at union square for the gary light rail system and you're going to
12:56 am
have to go before the voters to authorize and extend that. so you have to take the all that take into consideration. and also the way the gary task force final report came out we would have a service from gary and market to gary and laguna and go out the center strip to fillmore to masonic and straight out to the beach. read the final report of the gary task force and it was published in 1990 and all the other work published regarding a light rail system on gary boulevard >> thank you very much. >> any member of the public want to commit?
12:57 am
seeing none, public comment is closed >> madam clerk if we could have a roll call vote and a (calling names) the tomes passed. >> if you get call items 18 and 20 prelim and a item 18 a two year contract in an amount not to exceed 2 had the and plus and negotiate the contract payment terms and the non payment concerns. and item 20 approve the
12:58 am
appointment of the bus rapid transit community and this is an action item >> thank you madam clerk. colleagues on this i have a question and a possible amendment. the question is around geneva bus rapid transit. there's been a lot of concern around members of my district to make sure there's an effort to look at light rail along geneva corridor and the bus rapid transit perhaps there's a way to look at this towards light rail and it's important inform address the study that will be moving forward particle today. if i could get a response from staff or the mta on the feasibility of that analysis?
12:59 am
>> feel free to come to the mid again. on this item on page 182 with respect to the scope of the awarding contract. we included an optional task just to - i want to emphasis this is a short-term improvement of the extort transit district that's something to the development agreement that's going to be put into place. and the sfmta information on this the mta is interested in the operational benefits which could enable the transit to into up to the market street tunnel. and to not prevent access it
1:00 am
that facility. i'm understanding clarifying the revenue service ridership potential just recognizing it's two different ridership or travel routes so it could go up to the park and the rail line would cut off past bay shore. we can look at this in the stud but julie asked we confer with her whether there our report or consultants. if you can be flexible on how this can be done arrest or. >> one of the things we've been talking about because of the issues we've been talking about we're about to start a