tv [untitled] September 13, 2011 2:22am-2:52am PDT
2:22 am
trying to drill further into the hole, they have to rotate the casing. whether it is every hour or every 15 minutes or a couple of times in the middle of the night, they will have to rotate the casing. we will talk about that in a minute, but that is due to the fact that they are 240 feet down of a steel casing, and they cannot afford to have that lock up or freeze up because of the pressure. they will be using two rigs at the same time, two 10 or 12-hour shifts, and a swing shift that will go back and forth in an attempt to get back to -- we plan to have a production rate of 2.5 shafts completed per week, which runs the schedule out to 83 weeks. that is a total of 207 shafts in 83 weeks, which gets the work done in april 2013. we plan to start this on august 29 with the first hole getting started that day.
2:23 am
again, as i said, the two shifts during the day, there will be a need to rotate the casings throughout the weekend. the drillers as if they are above the halfway mark, they can probably leave it and not turn it in the middle of the night or on the weekend. if they are below the halfway mark, certainly, they will have to come in and rotate. whether it is every 15 minutes or once an hour or every other hour. another feature of the work is the traffic bridges and the trestle bridge that will run the length of the project. basically, the objective is to maintain traffic on first, fremont, and beale street, with a minimum of three lanes and the pedestrian lanes. in addition, in the east/west
2:24 am
direction, there will be a 30- foot trestle bridge to allow them to have equipment operating to assist with the excavation process. this shows you the layout of the trestle bridge running the length of the project, and also, you can see the cross lot bridge. they basically need to bring all the soil up through those cross braces using a crane up on the trestle bridge to do the excavation. they can go about 15 feet at a time, and then they start putting the bracing in. this is the actual excavation running from early next year, second quarter of next year through the end of 2014. they will start at the west end and work towards the east. that is primarily because in the east, we are still doing debauches pile doing the buttress piles. as i said, there are five levels of live skit that need to be incorporated at each one of
2:25 am
those various levels. right now, the plan is to conduct the excavation in two shifts. with the bracing going on basically during the regular daytime -- there would be some noise associated with that. be welding. possibly welding on the lot ships. it depends on the schedule. just to put that information in a graphic -- here we are on an july 2011. that is the intersection on the north side so we can do the assuring wall on the east but chris. by october, the shoring wall the east end should be completed.
2:26 am
that is the blue. the retrenching will be pretty much completed around the west end. and in january, the cdsm wall pretty much complete. it allows us to continue construction on the west and. then we start working on the traffic bridges. in july, the plan is to have all the traffic bridges in. you can see the excavation proceeding all the way up to be buttressed area. by the beginning of 2013, the excavations are complete down to
2:27 am
fremont street and to be buttressed area. it is completed, and the excavation is finally complete in 2014. the thing to note is in the west and, the whole excavation has to be complete before they can start the foundational work. this is just focusing on the work. so, if i can answer any questions? vice chair ortiz: are there any questions? director kim: we are starting to get information about this from the residence. if you could talk a little bit more about the sound of the rotating casings? >> sure. in reality, the sound of the casing rotating is minimal. is a high rpm diesel engine.
2:28 am
it would be comparable to comparablea bus revved its engine. i do not know if that is considered low or high frequency. the noisiest pop -- the noise is part of the operation is when they inject air and then have to do that fairly quickly. they take the case in al. they set it aside fairly quickly. the current plan, the ideal situation is all that concrete is place in the morning. what we consider a swing it shipped until 8:00, 9:00, 10:00. no promises. they may push that. the thing to remember about concrete pouring is once you start, you cannot stop. we are not allowed to add a
2:29 am
joint in any of these buttresses where the concrete hardens and you add it later. you cannot do that with this. it takes eight hours to 10 hours to pour. the plan right now is to get all those started in the early afternoon and finished them before the late hours. director kim: you think that could happen once an hour on the graveyard shift? >> the worst case we heard so far is a couple times and our. i was on a phone call with a driller last night, he reiterated that they may not have to do with all, but sometimes every few hours. director kim: my next question was -- this will primarily be covered during day shift? >> i might have confused you there. the excavation will go on in two ships.
2:30 am
that will be day and swing. swing those into the 11:00 hour. the big noise is setting them in place and rattling them around. the excavation is truckthe welde evening hours. with the ambiance traffic noise you probably would not hear a welding machine. director kim: ok. thank you. vice chair ortiz: any other questions? >> thank you, vice chair. that concludes my report. >> vice chair, directors, we have not received any communication of public suggestions on it that's item. vice chair ortiz: ok.
2:31 am
let's go to the consent calendar. >> ok, we will go to the consent calendar. directors have not received any indication that the public wishes to have any items sever. your items including the minutes of the june 9, 2011 meeting and item 7.2, authorizing the executive director dick skewed amendments to extend agreements for state abacuses service sees -- for state advocacy services with options remaining to extend each agreement for an additional three years. vice chair ortiz: is sarah -- is there a motion to agree to the consent calendar? can they agree even though we are not here? >> [unintelligible]
2:32 am
severed. [unintelligible] >> i will second it. >> he was not here either. >> thank you. >> do you want to consider it separately? vice chair ortiz: whatever. whatever is easier. ok, so we are voting on 7.2 first? >> the minutes. vice chair ortiz: is there a motion to approve the minutes? director kim: so moved. their minutes -- >> their minutes --
2:33 am
[roll call vote] director metcalf: i looked at them. >> 5 ayes and the minutes are approved. we will go ahead and take item 7.2. vice chair ortiz: is there a motion and a second? all in favor. >> aye. >> the consent calendar is approved and we will move into your bridget -- into your regular calendar. item 8 -- authorizing the executive director to executors renew professional service agreements for an amount not to exceed $28,400,000. directors, bob beck will report
2:34 am
on this item. >> thank you, directors. you have been our program management and consultant since 2004. we sought expertise in developing large-scale capital projects, as well as a wide range of technical expertise in transit infrastructure. and project management, construction management. and several smaller team member's proposed and selected as the preferred team and brought them forward for approval in 2004. we spoke with them during the
2:35 am
implementation of the program, as well as document management and administrative support. there were ancillary projects of bus storage and bus ramp construction. we had a first three-year term that ran from 2004 until 2007 into 2008 for the first three years of the program. that was renewed in 2008, and it is here for renewal again. the rfp did provide for only two renewals, so this is a contract we will need to put back out in the future. term of one was initially
2:36 am
authorized for $37 million and actual performance over term one, due to demands over those first three years, the total amount expended was $23 million. overturned $206,000. we have expanded roughly $31 million under that contract, and the spe performance was 32%. at the end of each term, we go through a performance evaluation. the team continue the commitment of quality personnel and staff members, the performance and working relationships with the various stakeholders and members of our consultant team.
2:37 am
the adherence to the annual work plans and task orders, both schedule and budget, and the quality of the liberals -- deliverables. we are bringing back the contract for renewal with the recommendation for renewal. i can take any questions. vice chair ortiz: are there any questions? i see there has been a motion. is there a second? thank you. ok, and members of the public, anything you want to address on that item? we will take a roll call vote. [roll call vote] so that's 5 ayes and item eight is approved. >> item 9, approving the operating assistance proposal
2:38 am
dated june 24, 2011 and in implementing agency resolution of project compliance for the amount of $3,950,426. >> good morning, directors. this is a routine funding resolution and required board resolution. this is the annual allocation of operating dollars. per legislation, it now comes to tjpa for temporary operations. this is just a routine request for the $3.9 million for operating funds. vice chair ortiz: thank you. is the motion? a second? director metcalf: second. vice chair ortiz: roll call
2:39 am
please. >> thank you. no members of the public indicated they wanted additional comment on that item. [roll call vote] 5 ayes and item 9 is approved. vice chair ortiz: then we go to the last item. >> item 9 is approving a resolution appreciation for nathaniel p. ford. >> we wish you the best in your next endeavors. moving on to former chairman ford's resolution . i would like to read it. whereas nathaniel p. ford sr. was elected by his colleagues as chairman of the tjpa board of directors, vice chairman from
2:40 am
june 2007 to may 2008, and chairman from june to thousand eight to june 2011, and whereas he has been coded his -- he is dedicated his career to improving public transportation as the director of the san francisco municipal transportation agency and the joint powers board, which oversees the operation of caltrain , and whereas we have benefited from the knowledge he has brought to the tjpa position for the past five years, and whereas as chairman of the board, the tjpa come pleaded and international -- completed an international design and broke ground and design at a ceremony attended by then-speaker pelosi, the secretary of transportation ray lahood, and whereas his commitment to the transit program goals directly contributed to the receipt of
2:41 am
$400 million in stimulus funds and the important recognition of his involvement in the transit program, and whereas he left his position as executive director of the san francisco municipal authority, now therefore be it resolved that the transit authority expresses its most sincere appreciation to nathaniel p. ford, and be a further resolved that we wish him continued success in all his future endeavors. vice chair ortiz: thank you. i wanted to add my words for the appreciation for his leadership here. >> i spoke to mr. ford this morning. apologizes for not being able to attend to except as. he says he is deeply honored and he appreciates this board for the resolution of appreciation.
2:42 am
222 Views
IN COLLECTIONS
SFGTV: San Francisco Government Television Television Archive Television Archive News Search ServiceUploaded by TV Archive on