tv [untitled] May 12, 2013 12:30am-1:01am PDT
12:31 am
have multiply make any sense we can work through. we were able to shut it down and shufltd it to other make any sense in the city >> i see you've been working around earthquakes suppose we get the big one how long will it take to get that fixed. >> if there's a water seismic break at the time there was a think earth quack but they were able to put back into either in a couple of weeks and other things took months later but if we have a larger seismic fist we
12:32 am
do have a well trained staff that we can come back and get minimum service into the area it's not just here in san francisco we have other customers that depends upon on us. we have some ways we can move sewage into our north plant but that's kind of a catastrophic event and it depends upon how much damage >> a couple of weeks may not be enough time. >> it all don't understand the process. >> so there's 20 million gallons. >> a lot of it is the financial
12:33 am
district if they're not people working downtown after an earthquake the amount produced in the work city fluctuates. i guess i ask those questions you have good attorneys who look into this >> if you had to buy insurance or some sort of bond to pay for this risk how much? >> i don't know. >> my sense is quite a lot. >> the risk during employee and post construction is outing put
12:34 am
on the developer. >> so again as we've heard from the district attorney if those units are solid off those risk goes to the condo owners. >> i've heard that but i don't know. >> so the individual condo owners might be on the backs of them but there's a huge risk and it falls back on the shoulders of the city we'll have to pay for it. >> i assume that the risk b will fall on the city. >> why don't you continue with your presentation. >> i'll go back. things we're going toication
12:35 am
do some assessments precondition assessments and be able to use those to compare the pipes and the 10 by 10 sewer during construction and if there's anything we can judge, you know, to be taken place we'll ask the developer to fix those. as i settle in this area you can cause differential settling. we we'll tell you have a remedy in place. as we talked about there will be an emergency repair plan and we talked about this if there's a break in this pipe and there's sewage to causes problems to the
12:36 am
public health we have a state agency that oversees our permit or any municipal storm system requirement. and finally the contractor would have to have a work plan to protect that >> so this those are preconstruction activities that have to be in place before the construction. >> and finally those are the agreement they restrict our facilities you can't plant trees on top of our structures or build anything. this is a typical thing we do with all our easements if somebody's using them for recreational activity.
12:37 am
so that concludes my presentation and i'd like to answer any questions >> again thank you for answering those questions. actually, i have a number of questions about i i was hoping you'd address in the report that your agency call for. i want to say is the engineer who prepared the resort here? >> he's in new york. >> i may want to call him. >> we didn't have enough notice to get him out here. >> are you familiar with the report? >> no, i have engineers here but i hired an engineer from outside and that's their opinion
12:38 am
and their work. >> can you tell me where why the report was commissioned? we'll >> we'll rely on this complex report so it's not inside our organization plus this specific person has the expertise. so the report cost the city $135,000 and it took seven months it started in the middle of july last year and is report was released february 22nd. you've had a chance to look at it >> it is a fairly address threr
12:39 am
four sections so section 4 describes the risk to the puc and the section 57 refers to adverse effects and section 6 talks about the design. >> so section 4 do you recall what the risks are to puc assets from the construction? >> no, i don't. >> i'll read a couple of lines the primary certain is from grounl movements to waiting instability and it may include angle disburse movements and it
12:40 am
might effect the construction induced have i been arbitrations could cause damage. >> no. those are common things we deal with you adjacent to our property and. >> if we could talk about the adverse effects. your aware we're in wealth e earthquake country >> i was born here. >> if you could go to the slide i'm sorry go back one. and if i could read under seismic erroneous the report indicates there's a 63 chance of a earthquake with strong to very
12:41 am
strong shaking at the project site does that sound right? to you >> yes. >> we had a brief conversation around the developer was going to design this system with an ice based on system and ultimately decided to do something else and not use that base isolation system? >> do you want to do this? >> who knows how to handle earthquakes.
12:42 am
>> it would be talking about the base isolation actually this building is on a base isolation system it's isolated from the ground from an elastic a moveable base. >> so it stabilizes things a little bit better. >> right the building is that. >> now we looked at that but decided to go something else? it that right? >> yes and if you want to ask the developer again, we don't have the final plans in speck so it's hard for us to discuss this. we'll also assume worse case
12:43 am
until we get the specifics there's more movement and we have the vibration monitoring plan so if differential settlement through that >> can you have a representative address that or we could continue on? continue on. so in the report it states that after the consultant puc the system was being eliminated from the plans the assistant requested an analysis showing the impact of the seismic analysis. about the analysis that was done those methods and assumptions
12:44 am
are not appropriate because til strong shaking and that includes stiff floor slabs and are you familiar with this issue in >> i respect there portion of the report and i didn't. i'm familiar with the issue. i think that's one of the reasons we're asking for more sophisticated analysis in how the building would reaction in an earth quack >> my understanding was the developer decided not to use the more expensive materials to save
12:45 am
money. is it fair to say that this is why you decided not to make building more safer and i think it's absolutely pertinent in part because your decision not to use the base isolation system is not going to lead to the city in an earthquake >> if you'd like to come up and say that on the microphone. it's hard to hear you.
12:46 am
>> simon at san francisco waterfront partners. >> erick engineer. >> what i said mr. president, was that the question was asked by the person who perpetrated the report and would the design without base isolation imexpose a greater risk open the system. >> i'd like to again erick wong. i'd like to state that with base isolation or without base isolation on a standard 6 believe it the standard - the question is what does base
12:47 am
isolation do stem from understanding of how forces are taken down from the superfluous structure above down into the soil. and it was our conclusion that the amount of force and with or without the base isolation system has negative impact with the force onto the soil and the adjacent >> okay. i'm trying to understand that. conventional ways is you build a fix base and it means under the building it's constructed to have a little bit of flexibility so in shaking the building can absorb the shaking
12:48 am
>> so the sub structure the 3 story parking abandonment is a fixed sub structure the base isolation is at the gund that's why the comment was not relevant in this conversation. >> so you're saying the base isolation stabilizes what is above the ground. >> they're both stable. >> right but the isolation - >> it will reduce the accelerations that travel up into the building above and so it makes it more stable?
12:49 am
>> that's what i want to understand and i understand base isolation systems cost more. >> there are savings that the base service stations allows for yes base isolation system but because the building is less above. >> when the building doesn't come down. >> the cost is a wash. >> i appreciate that. and while you here can you answer is a couple questions around liability. again, we're hoping nothing happens but if there's an earth quack are you willing to assume the liability during that
12:50 am
construction and afterwards? >> first of all, mr. president, the area of the building is going to be a public park that will be owned by the port of san francisco so nobody's going to be building anything else on it it will be a public walkway. as far as liability not unlike any building in the city that's built next to a sewer pipe the liability the ongoing liability is limited to developer and subsequent owners there will be owners who will belong to a
12:51 am
homeowners association and they'll have insurance so the liability will stay with the city. >> so in other words your liability will be limited to the construction but once you've sold the buildings you get to walk away. >> well, the homeowners association has the port of san francisco it will be maintained by the homeowners association sea any activity of the homeowners association in the maintenance of the above ground area the homeowners association would be liable and if an earth quack happens today and the pipe is damaged the private club that
12:52 am
sits and i top it right now the city can blame them but like now the city infrastructure theenter city is responsible for the infrastructure. so i did ask a question before around - don't worry simon they're not coming for you >> and asked a question. >> your investment i'm wondering in you could tell you you mentioned you had liability and i assume that california stares has a responsible. >> the shareholders is a private entity and got you. and i had a couple other
12:53 am
questions but since you're here i noticed in the report if you'd like to leafy, go back to the puc >> so are you familiar with the fact that there are portions of washington site that are classified as wastes sites? >> you mean the development site? for it was noted that the ground asportation the exist site as california hazard wastes based on the soil samples and they're high they're highly poison news and
12:54 am
an unplanned rupture could release foul smells and it remains a protrude liability that. >> i seem if somebody is classified as hazard wastes that should have been i don't have any knowledge of that. >> shouldn't it have been in the addendum? >> i assume there's a measure for that but i'm not sure. >> we'll have an opportunity to ask planning. if we could gone to section 6 in
12:55 am
the washington design if i can read into the record the level of urban certainty is = validate below and i assume i gathered from our commitment there's additional studies to be done >> correct those are caveat and we don't have sub surface information. the site conditions may be different then anticipated. so again even in our construction projects we have those concerns and can have votes we'll encounter different
12:56 am
situations as this project move forward >> were there plans that you didn't receive? >> if you could go to the next section so let me just read the 8 washington team has yet to submit review that are sixth and they include conflicts with maintenance repairs and examinations of those facilities the increased risk to the puc because of the close proximity and the strain in the ground
12:57 am
imposed. this was requested any your engineers to the developer i'm wondering if the developer has any information why this information was not forget coming to the city? >> if you want to step up to the microphone. >> i believe the draft your reading from is 22. the whole matter has not yet been concluded i'll say this is a study that's been going on for misinforming - going on for
12:58 am
sometime. we have our engineers who designed the system but mr. president, this report is something that's not yet concluded. if you probably read on we need to do some modeling. the puc will require of us some seismic engineering commuter modeling. there's a lot of details left to do. normally with any building the process of designing the sub structure foundations is done by the contractor they're here. after the contract is awarded. the general contractor then
12:59 am
selects a subcontractor the subcontractors selects an engineer to design the shoring system. we were asked to accelerate that process >> so you start before the final permit? >> the "x" vacation contractor retains the services of an engineer who prepares the items you're talking about. and it's done in every building in the city. we were asked to accelerate that at our expense so this entire design we agreed to do out of respect for the puc and wanting
1:00 am
to make sure we're or in the same page. that hadn't been done. we're still in conversations with the puc. we haven't seen the agreement yet but in that particularly course our engineers and the pucs engineers will be agreeing on the safest method to do this >> so you're saying you're not able to do the final analysis until the permit is done? we're in the process of doing that >>
48 Views
IN COLLECTIONS
SFGTV: San Francisco Government TelevisionUploaded by TV Archive on
