Skip to main content

tv   [untitled]    June 18, 2013 12:30pm-1:01pm PDT

12:30 pm
in movie this project forward. as a driver i have spent 45 minutes and someone who's frustrated over the challenges in parking in san francisco. i have to put that aside in the interest of dealing with public safety appropriately. i do want to work on possible solutions so we can at least try and mitigate some of the impacts of this project. this is a really important project and i'm prepared to work on doing what's necessary to make the changes around ambulance assess and some of our large fire vehicles and their ability to assess the area and the mooney buses for the seniors. i'm prepared to look into those concerns and make sure this plan
12:31 pm
properly addresses those concerns but at this point, i'm prepared to move forward and support in particular item today. thank you so much for your time and providing us with the input on this project so we can make the possible changes for your concerns >> thank you. i time to reiterate this is not just the ma sonic project but a lot of projects in our one grant cycle and $35 million we're looking at today. confirmation yee >> on this particular item i agree with supervisor bred. i wanted to ask the question -
12:32 pm
one of the things as an advocate for pedestrian safety i think one comment that someone made is that we've got to put safety above all. it's going to inconvenience a lot of things. but one of the things i've noticed about the strategies as you take away washing we need to also look at that whole situation if you're trying to make things safer and part of the strategy is to take away parking because of the traffic coming is that we need to pit more energy into what's the solution to helping with the parking lot. mainly because i say this
12:33 pm
because my observation is that what we end up doing along the main corridors is punishing those residents along those main corridors that need the parking space for people to go through their resident. and i look at at the 19th avenue. it's how we try to find solutions to the safety sea basically as we look at solutions some of it seems to be punishing the residents so people can traffic through the area. so i think ma sonic is in the same situation where most of the traffic isn't about the residents there. we need to really balance how we look at the solutions. thank you >> thank you confirmation kim.
12:34 pm
>> thank you i want to speak to some of the other items and really want to thank the transportation authority for working with our office. connecting market and downtown all the way to the ballpark so we're excited about this being a portion of this project. so this funding is going to be incredibly important in the heart of san francisco's denounced. i mean hopefully caltrans and the bike and safety improvements are coming forward. sitting formerly on the school board it was - we understand
12:35 pm
that there's a number of pedestrian safety issues around the elementary school to i think it's important we prioritize so make sure that our young children o are going back and forth. >> yeah. i want to add to commissioner kim's comments i think the pedestrian improvements though it's reduced by 4 million it's going to be covered by prop k funds. its critical as well as the china street i was there for the festival. i think there's some wise projects and save routes to school as we leverage money and other resources that's so
12:36 pm
important not just for jean parker and many other schools. i was active in the ma sonic area i'm looking at the design study from 2010. i think there's at least 3 town meetings. so north of the panhandle it was liveable city. no looking at how a street design can make it a more liveable city. i think narrowly baselines makes a lot of sense.
12:37 pm
whitney young and some o so much of a concentration not it mention the pre k and child centers but it's a boulevard in need of major planning. i think the boulevard went through a major process and as i recall i do think the mta should be moving forward and reporting back to us so on traffic conditions as target comes in and i know that supervisor bred have called for a hearing before the neighborhood services where we're going to hear from target on university associations but on the other side of gary and ma sonic where the trader joe's is
12:38 pm
happening but my hope is the mta will reportedly back to us hopefully by fall. that looks at not only permanent parking hours but other types of expanding residential parking and the other part is though we maybe set up on the mta toes we should be looking at is concerns. i'm in agreement more could have been done and what will happen with the loss of those parking spaces especially along the corridors. so i'm supportive of the thai million dollars and a number of those grants and i think that ma sonic promise it will help us so i'm supportive of the funding.
12:39 pm
and i'm wondering in oh, commissioner bred and so if there are no other comments can we approve this without objection. call item 5 >> yeah. recommended 1 million 2 hundred and 49 million with the san francisco safety program this is an action item. >> good afternoon this item begins on page 43. as you recall we provided i 90 in april. san francisco share of the
12:40 pm
region and safety school funds is one-hundred 4 million over the past few months we're worked with the safety coalition for how to enhance the safety issues. we have a - we have the san francisco program. the primary difference is the program will increase in size from a number of 16 high schools. if you have particular schools in mind to make sure the coalition reaches out to call the authority staff. and we're provided you with a brief presentation or if you feel that the april presentation
12:41 pm
provided sufficient information we'll skip it >> yeah. given the need for this room. i heard a very important presentation so i'm hoping we don't need that presentation today. so seeing no questions let's open this up for public comment. seeing none, public comment is closed. colleagues can we move this forward. madam clerk rewe needing to vacant this room >> we need to vacant the room. >> so we need to call items number 9 first and then we'll proceeded to end this meeting as quickly as we can. >> item 9 is an forgotten item. >> anyone from the public who
12:42 pm
wishes to speak. >> i want the transportation authority to look at in we talked about this but i'd like for them to implore funding for the key drive which is a project that i think costs a little bit over a million dollars. i actually have a cost estimate and a breakdown. and it's possible to look at the funds we have available to begin f that project for next focus year i'll be happy about that >> thank you. anyone from the public who wants to speak? seeing none, public comment closed >> item 10 public comment. >> we have one card anyone else
12:43 pm
please come forward. >> i want to touch the queens bridge and start by thanking staff. last time we were told that puc has no plans to vacant queens street. if you include the $3 million of the queen street track. the time has come to take a fresh look at the ocean study starting with the queen street underpass par this is what it says that the queen street bridge doesn't have the sufficient length. this presents a good opportunity to incorporate the proposed
12:44 pm
station requirements into the bridge. on this basis i hope this committee will recognize this extraordinary opportunity and focus on the efforts of the designs and starting with the queens bridge >> thank you, sir i will follow-up and make sure i'm checking in with staff so if appropriate that's brought forward. seeing no public we'll close >> next item is adjournment. >> thank you very much the meeting is adjourned
12:45 pm
>> good morning and welcome to the transbay joint powers authority meeting -- special meeting for may 20. my name is jane kim and i will be chairing the meeting. could we take roll call. >> director harper. >> present. >> director lied. >> present. >> director metcalf. >> director sart art. >> present. >> and chair kim. >> here. >> kim present as well. madam chair you do have a quorum. >> thank you. are there communications from the board today? seeing none any old or
12:46 pm
new business? seeing none we move on to executive director's report. >> good morning directors, members of the public. as you know we put out our seal bid that can be broken up into three packages recently and bids are due june 20 and after that he we expect to bring a board for your consideration to the july board meeting in order to stay on schedule so that's really the main item right now in addition to the 100% cd's minus the it component us due at the end of may and that is on back to be delivered to us and we will review that with our team members and turn the package over to webcor by the end of the year at the latest and i will have steve give your construction update. >> good morning directors.
12:47 pm
steve rule with turner construction providing cmo services to the tjpa. the last month has been another good -- make good progress overall on the project and again no injuries or osha reportable accidents. we had one near miss accident involving a crane losing some sort of loss of power in the lifting and a piece of equipment falling back into the hole. no significant damage to the equipment and no injuries whatsoever. they were following all of the appropriate procedures keeping the hoisting area clear so there were no injuries and work is continuing in the area. the excavation is about 72% complete overall and the micro-piles are 50% complete and zone one and 50%
12:48 pm
overall. the demolition continues in zone four as they start to work on actually demolishing the tops of the shafts and continue to work on finishing up the quality assurance coring of the piles. the geothermal installation started in earnest in last period with two sections installed and tested and covered up in prepareeration for of the mud slap and the water work continues along mission street particularly in the intersections at second and first street to finish those areas up. again the awss and a replacement or increase in size of the existing system which leads getting back into the other utilities around that one and that is slowing the process down a little lit but all of the other utilities are cooperating in moving their materials
12:49 pm
around in the layout. we will see the completion of the micro-piles within 90 days and zones in one and two, but more significantly what we should see is the first foundation pour, the first map slap poured in zone one should occur in july. you will start seeing the reinforcing steel and the waterproofing. we first do a waterproofing layer and the protection and the reinforcing steel and the first pour should occur in july. overall all the timeline continues to zero in on the 2017 october date of operations with the below grade work starting up. super structure as the executive director mentioned we put the steel package out to bid. that will get that moving along. the exteriors and so on through the finishes. some milestone dates that we're tracking and continue
12:50 pm
to show you as they change or improve. of course the final traffic bridge was installed in april and with some float left over. some of the other items the first map pour is on track in zone one completing the excavation in first quart of 2014 is still on track and so on through the activities. the bse timeline getting towards the end of that with the completion of the traffic binge bridges and the excavation is 70% complete on. >> >> and on track for the beginning of 2014. as we go into the below grade work and up through the lower concourse and the horizontal land improving and the foundation walls and slap and box walls and we're in
12:51 pm
the beginning here with the and i will show you pictures and this will allow them to move into that waterproofing. the excavation status i know it's difficult to read, but it has the micro-piles which are in red if they're not completed and grayed out if completed. on the lower left hand side those are where the must be slabs are pored and turned over for the below grade work. the areas in the upper left hand corner is the next mud slap pours and that will be turned over to them by line five or six. give them about six bays to work on the first foundation pour. just some progress photos. again
12:52 pm
since everything is down below the level of the street it's hard to tell that significant progress has been made but can you tell from the shadows the excavation is deeper than the previous month. here is the micro pile account and with all of these piles installed. almost completely tested in zone one. we are completely installed in zone one. to date we haven't had failures of the micro-piles and the graph from before and they're staying on schedule and not indicating any problems with maintaining that schedule and keeping up what is required for the below package to proceed. so those are shots of the micro-pile work in zones one and 2p and as i mentioned the geothermal got started in
12:53 pm
earnest this period. it's about two or 3 feet below the surface what would be eventually covered by the mud or protection slap and you see the header system where all the pipes go into and eventually up the wall and used later in the project tied into the full circulation system of the cooling and heating water. i will give you some other ideas of the geothermal and of course once they're pressure tested and signed off the area is covered up again and prepared for the mud slab pour which in this area will be this friday. waterproofing mock up was completed. it subsequently developed some good questions and collaboration with the design team to make sure all of
12:54 pm
the waterproofing issues are covered and that mock up came down and they'll begin shortly. some of the other waterproofing activities at the base of each of the micro-piles it has to get waterproofed. that's the small area that look like reinforcing bars sticking up. those are the micro-piles and in the lower right hand corner they're mocking up the column protection. those columns are supporting the trussel or supporting the bracing and thigh all need to be in caseed in a steel jacket so they can be cut off at a later date when the trussel or bracing is no longer required and that area can be sealed up and waterproofed as well. as you can imagine that all gets covered up by the foundation slab that is 5 feet thick. some more shots of the mud slab going in. that's on the south side of the train box
12:55 pm
at the west end. excavation proceeding in zones two and three. zone four again all the water -- all the water treatment plant equipment has been removed. the trestle bridge is started. as of last friday was completed with all the deck cover laid out. they still have welding and work to do underneath, so work is progressing significantly in zone four as well. shots of the work going on in zone four. and of course i mentioned the awss work continues. you can see how congested things are in trying to build the new boxes for the pipe and work around the other utilities. this work was taken place at mission and first street. we still running overall the 63% mark on local
12:56 pm
labor. there are the break downs through the end of april, and as far as trade break downs also through the end of april 1300 unique individuals having recorded time on the project. and again this is just the transit center work and the utilities work. it doesn't include the previous demolition or the temporary terminal work. are there any questions? >> director harper. >> yeah. a couple. do you know what cause the loft of the crane power? >> >> i was told there was a hydroic system in one of the cable drums. it actually didn't free fall. it went down at a higher rate of speed but it wasn't a total loss and free fall. >> the other question i am not unfamiliar with the geothermal aspect. did we dorph that on
12:57 pm
the site? >> no, sir. good question. as placing the pipes under ground at that level there say constant temperature in the ground and so by pumping either hot water down through this system it's cooled to that constant temperature or cold water can be -- >> it's just a heat system. >> yes. >> okay. >> basically it maintains -- we use the core temperature of the earth which is at 40 some odd degrees to heat and cool the facilities. it's one of the first facilities in the country to use geothermal pipes for that reason. it helps with the lead points. >> i was wondering what you meant with that. >> it's interesting to look at if you're ever in the neighborhood. >>i definitely want to get down there. >> any other questions? >> director reiskin. >> yeah, i mentioned i was up at a office building adjacent to
12:58 pm
the site and it was impressive to see the magnitude of the work and you can see when you look down and how much excavation is getting done. the progress is pretty impressive. just one question on the schedule and i apologize if i asked this before. the schedule on the completion of the steel now shows september 15 which is better than the baseline schedule of november 15 and i am just wondering is that based on the current structure of the steel bids in terms when we expect to get to ntp and the duration or do we expect that to be reicized? >> good question. so the construction milestones that i just showed you that are in the update as i understand it not inclusive of any final impact we may discover with the steel bids. however, we believe that
12:59 pm
we can control that and that's what we're working on once we get the bids back and i know webcor is working on ways to do work arounds and strategize how to increase the speed for delivering the steel. i have seen some milestones that stayed pretty darn close to where we want to be but that will be discussed i believe if not next month the july meeting when we get the results from the bid but it's our intent to minimize that as much as possible and one is the discussion of the cast nodes and later on the agenda. >> yeah director -- i asked them to look at at schedule again and revise it based on everything and give me mitigation strategies if they believe there is an intent in any area tell me where we can recover and the float that we had back and i expect to have that back by the time we bring the steel package
1:00 pm
in july. >> okay great. thank you. >>i want to thank everyone for the good work on the construction site. we continue to have zero incidents and there are tours from high schools in the area coming into the site and learning about construction and engineering and architect and you are we will be bringing more information on that. we put out a newsletter that talked about two of the successful programs and manny says everyone he talks about we want to work on transit bay and it's the one project we want to work on and it's a testament offed good work andtur. that concludes my report. >> thank you. as the summer heats up we have interns and students coming in and maybe we could put them on the agenda for july. >> sure. i would be happy to. >> okay. now were