>> could we have a motion to excuse commissioner cohen? and we will take that without objection, and would you please read the second item on the agenda. >> item, 2, citizen advisory committee report this is is an information item. >> thank you, good morning. >> good morning chair peskin and commissioners. i want to start out by saying, on march 24th, two members of the cac and myself and tanen received a tour, and with one group remaining, and it was the planning department staff that have prepared the e-mail notification system. >> i am glaed to see that is getting fixed. >> thank you. item seven, most of the questions in the request, regarding the brt will be resolving around the lawsuit and
12:02 am
so we, for that reason, we didn't get a lot of up date on that. and then the other item was by the coalition allocation, and i want to pointed out and i did point out to the staff, that we give the ta gives a lot of money to the bike to workday. and i think that our acknowledgment on the bike key ligs website should be greater than others and so hopefully we will get a little more acknowledgment about how much that we are doing for the bike coalition. item 9, the interchange, improvement study, this item is near and dear to me as the frequent user, who is chased by the bike traveling at 40 miles an hour or more and who has seen, many families and others, crossing to get to the farmer's market. this was brought as a concern to campos and taken up as a major
12:03 am
project by rohnen. by the community members of which i am the chair. i have to commend the staff on this and the out reach to get us where we are and the commitment to work with commissioner rohnen and the neighborhood to be sure that this will be completed in our lifetime. and reconnect. and item eleven, i wanted to talk about. cac members noted the shift of concerns towards and beyond the southern parts of the city as perhaps being indicative of decreased affordability. removal of certain blocks, and they have the indication that more people were moving into these areas and that this will result and i am having the lessbility for the funds based on no longer being considered a community certain concern, sorry. >> the staff suggested using the
12:04 am
block method, did not mean that this is the case. they would benefit from being adjacent to coc, and on that i will. >> thank you. >> are there any questions for mr. wadling? >> seen none, is there any public comment on this item? >> seeing none, public comment is closed. that is an information item. mrr clerk could you read the consent agenda. >> three to four, and these are considered are you turoutine, i object, any of these items may be removed and considered separately. >> would any member like a presentation on the prelim results of bart perks program which we have been briefed on in the past? any members of the public that would like to comment on the consent agenda? >> seeing none, public comment is closed. and the minutes are adopted. and why don't we move on to item
12:05 am
number five. >> roll call vote. >> roll call for and that is right. on the minutes, roll call. >> made a yee and seconded by shehi. >> breed aye. >> far ril absent. >> fewer, aye. >> peskin, aye. >> ronen naye. >> safia, aye. >> tang? >> aye. >> yee? >> aye. >> minutes are approved. item five, please? >> adopt positions on state legislation this is an information/action item. >> mr. watts? >> thank you, chair and members and i am here to be finally to give you an overview of the passage of the transportation
12:06 am
finance bill. but first i want to just indicate that in the packet you have several select bills that we are monitoring and watching, and no new bills are being added on at this point in time and some new major policy issues will be in the coming weeks and i anticipate the legislation in that arena emerging and we will deal with those at that point in time if that is to your satisfaction. >> in addition, the staff prepared an updated memo of last week's member though that went into the package to talk about the transportation funding is now out of date. briefly for an overview perspective, sd one is produces over 5 billion a years, roughly estimated to be 52 billion over a ten year time horizon. from the taxes increases and it
12:07 am
looks as if half of the road repair is dedicated to local governments and the other half is retained by the state and there are some other transportation elements that the state would contract to control or exercise control over. >> and the last that i heard that was 22 to 28 million, for the street repaving for san francisco. >> i believe that is what i have here is 17 and a half million. of maybe rises to it has a built in index and so the 76 is the reflection over the ten years. it gets low and gets up over the 20. and i would like to tell you about the tax and go into more detail on the local impacts and
12:08 am
wrap it up. if that is okay with you sir. >> mr. watts, we have all read a lot and we would love to hear it from you. >> i can't tell you all of the secret stories, but if i could figure out. so sb one has essentially has four new tax or four increases in taxes. the gas tax has two components, the base gas tax which we have had all along which is the 18 cents a gallon, as well as the price based tax which was the conversion of prop 32, on the excise tax. the base gas tax is raised 12 cents and it begins in november of this year. it was set at that date because that is when the summer blend comes off and they felt that there might be a price adjustment that will accommodate the increase in the tax rate at that time. >> in addition the price based tax that i mentioned, is already
12:09 am
geared to go up two cents a gallon july the first, on the board of equalization and adjustment and they will let that adjustment happen one more time and they think that it is going to be three cents and then in 201 #, they will set the price base and stop the annual adjustment process to the board of equalization, at the 17.3 cents, and so in essence and it will result in a base of 30 plus the new fixed excise tax at another seven and a half cents on top of that. >> so a doubling of the gas tax. >> it is for i have not heard it say that way, straight forward. >> the diesel tax is raised again simply to the gas tax in the fall. and that is a 20 cent per
12:10 am
gallon, for the diesel foo ul and that raises $720 million through that ten year averaging and there is also a zero emission vehicle tax that does not go into effect until 2020. the governor described it himself as he is trying to balance initiatives that he sponsored and supported that encouraged folks through incentives to purchase zero emission vehicles and didn't want to have a heavy zero emission vehicle. that proceeds shgs and so he delayed it until, 2020, and so that was the compromise that was worked out there. and that would be $100 a year. i don't know the name of this fee, but it is a hi brid registration fee it is not in the law but it acts like the vlf
12:11 am
12:13 am
the shift 145 million as stipulate you lated for the cycle coming up. and as i understand it, there are major capitol investments that are intended to be recipients of the portion of it going forward. and on the state grants to transit agencies there is two parts to that and i mentioned the diesel sales tax and in addition to the portion of the new hybrid readministratigistra. and on the diesel sales tax that is flexible and it be spent on operations it is allowed to be spent on operations or capitol. and the mta here in town and pardon me. and here in san francisco. 27 million, and bart will
12:14 am
receive, 4.9 and cal train, 3.9 and the portion that is transferred from the hybrid registration fee will be dedicated to the capitol purposes because it is more directly tied to article 19 restrictions in the constitution. and mta would receive 11 and a half million, and bart 6.3, and cal train, 1.5 million of that for the state of good repair and the other capitol purposes. the total it looks like the annual amount coming into the city, is over, 65 million dollars. and as i calculated it on the annual basis. and there are some competitive opportunities for agencies here. the ta and for mta and bart and others. there is a transit and inner city rail, there are the passenger rail fees and that is not competitive and i apologize
12:15 am
for that. active transportation, some planning grants, and there is a new category that receives a quarter billion of a dollar a year over the next ten years. and that would sum up my presentation on this, i would be happy to take questions, and i have one more topic on the cap and trade and conclude. >> colleagues? any questions on senate bill number one approved by the state legislature last thursday. good news for this mu n municipality for the state of california. >> for for mr. watts, but i know that the ta staff asked if they would present and mr. watts did a great job of what is coming to the city and county of san francisco that they will present a visual to help commissioners understand the break down.
12:16 am
>> on that point i am not good at technology, there in is your packet a summary and also available on the computer, if i knew what i was subpoenais u su dochlt >> this is actually the simplest technology and all that you have to do is lay it down and bang it pops up for everybody to see. >> there you go, a poll guys. >> no wrryes. >> and that lays out the 17.6 million that mr. katz referenced as well as the additional operating and state of good repair dollars totaling $66 million that were set forth. any questions commissioner kim? other members? mr. watts would you like to move on to the other piece of legislative information. >> yes as you may have read there was a recent app ellat
12:17 am
court and by all accounts everything that i have been able to pick up with the conversation of the administration and the other folks involved, it looks like either side had committed they are going to keep raising the issue up to the next court level and while that is going on, there is still the issue that even if it is validated as not being atax, it still, and it ends in 2020, and so the administration and some of the leadership who have been working on this transportation package are ready to shift gears and go to the extension of cap and trade and i think that they would hope to achieve a two-thirds vote level so that it, and it neerz it from any further attacks going forward. >> are there any members of the public that would like to comment on item number five? >> seeing none, public comment is closed.
12:18 am
colleagues, do we need to or let me defer to the staff. do we need to take any actions because there is no new, there is no new positions being taken. so that will be an information item. and we will move on to item number 6. mr. clerk. >> item 6, a amend the adopted fiscal year 2016/17 budget to increase revenues by $13,396,777, increase expenditures by $15,356,835, and increase other financing sources by $21,335,835 for a total net increase in fund balance of $19,375,777 >> miz fong. >> good morning, deputy director for finance and administration. and what you have before you is a presentation of the fiscal year 16, 17, budget. and amendment, and i first would like to recap just what the ta budget includes, it includes sales tax revenue, sales state
12:19 am
and regional grants and the vehicle registration fees for the prop aa and the fund for clean air, and revenues. and the treasure island, mobility agency, and expenditure and revenue and our capitol projects and our capitol expenditures operating and admin and service costs. >> in terms of the ta budget we have budgeted adopt a budget of $125 million. 87 percent of that represents sales tax revenue, while the remaining 14 percent represents federal, state and regional grant and prop aa vehicle registration fees. and internal interest income and other revenues. they have adopted a budget, and this represents 96 percent for
12:20 am
the prop k, aa our tfca and our projects. and the remaining four percent represents personnel expenditure and non-personnel costs that reports the office rent and lawyer fees and legal fees, and the odysseys and in addition to the office supplies and things that run in the office and also, includes within the four percent, our revolve it credit loan costs. >> for those people who are listening carefully, and just heard that our expenditures are twice as much as our income, would you like to explain that to everybody who is watching? >> yes. as everyone may remember, we have approved a loan from the resolving credit agreement. and this loan in addition to a bond would help to fund the division between the $125 million, and the 120 million of
12:21 am
expenditures. and we will be bringing before you the physician calling year of 17, 18, in the months of may and june and there you will see a bond that will also come before you for your approval. >> thank you. >> okay, and moving on to the budget amendment now. >> the budget amendment is our opportunity to take stock and changes in revenues recognizing new grants and in addition to acknowledging unforeseen expenditures and reflecting any new information that has come before us in the past nine months. and for anyone who has a packet, and or is looking at the budget on-line, attachment one is your executive level view of the ta budget and you will see each fund represented in addition to what the exhausted budget has. what the change is and what the new proposed budget would include. >> attachment two is a detail level of review, specifying every single grant in addition
12:22 am
to each detailed line item of expenditures in addition to those changes related to them. and attachment three is a line ilt em description, explaining each increase as if and increase and decrease in our budget amendment. and moving forward to the actual major changes in the revenues, and expenditures we have a few new grants and we have the south of market freeway ramp intersection grant for $77,000 to add to the budget and this is to develop a priority set of short and medium and long term safety improvements and we also received a commuter hub study for $70,000 to evaluate the shuttles on the neighborhood safety and the environmental and the public transportation, we receive the additional, 621,000 commitments in the tida for the treasure island, mowbility agency and this includes the park and management plan, in addition the board has approved
12:23 am
$800,000 for the geary and the bus rapid transit and this was for environmental analysis to address community input in addition to the time to work with fta and includes the cost for the legal defense for our err. we have the island that is for the major projects to the year. we are carrying forward in addition to the winter season that the project has, and suffered through. and delays in the tree removal and foundational work caused by the early nesting of birds in the construction area. and in addition to adding some additional scope for the vista point as well. and we have also experienced this project delay in connect to success and due to the longer than anticipated start up and contracting process. >> and we also have an increased to the administrative costs and we have included budget amount
12:24 am
for the development of a potential 2018, local revenue measure, in addition to adding some additional cost to help to maintain the ta's accounting system. >> and in total, we are seeking increase in 7 percent in our revenues for approximately, 15 million and increasing for 7 percent revenues. we have included a $25 million draw on the revolving credit agreement. we received the invoice request for reimburse amount for the vehicles and we are anticipating more of those invoices to come in the next few months and have requested included the 46 and million, and pull down from the resolving loan as authorized by
12:25 am
the board in 2017. and here you just see a chart of just how much additional resolving credit agreement that we have pulled down, with that i am more than happy to answer any questions. you may have. >> do you have any questions relative to item six? seeing none, are there any members of the p you believe who would like to testify on this item. >> seeing none, we will close public comment. we have a different house could you read the role. for the budget. >> yeah, motion first? and this is the interesting thing and when we are on the agenda, and the motion made by commissioner yee, and seconded by, commissioner tang, and on that item, a roll call, please? >> on items six, commissioner breed? >> aye.
12:26 am
>> fer relevant ril. >> aye. >> fewer. >> aye. >> kim. >> aye. >> commissioner, peskin. >> rohnen. >> commissioner safai. >> aye. >> shehy. >> aye. >> tang. >> aye. >> commissioner yee. >> aye. >> the item passes. all right, the next item please. >> allocate $193,475 in prop k funds for bike to work day 2017 and the central richmond neighborway project, with conditions, and appropriate $602,254 in prop k funds for the geary bus rapid transit project, subject to the attached fiscal year cash flow distribution schedules . subject to the attached fiscal year cash flow schedules and this is an action item. did you hear mr. waddling i thought well, laced admonition. all right? >> i did, and i can address that as well. >> excellent. >> i will do the first two requests and hand it over to my colleague. >> all right so this morning, the first request is for a
12:27 am
promotion and an event day services for the bike to workday, 2017, which is mail eleventh, the events include energizer stations, to receive, information and bicycle repairs and refreshments and it will be promoted and the statements will be located across the city. and the san francisco county, bicycle coalition will be the leader and the organizer. and each year, the sfmta conducts accounts to evaluate the effectiveness and see the increasing participation including 13.6 percent, survey shows that many people have started biking because of bike to workday. and bike to workday is listed in the san francisco bike strategy as a tool to help to normalize the transportation and grow the mode share. and to speak to mr. waddling's point we do include a note in
12:28 am
our -- and it kind of, and it is on the page 83 of your packet. and just as a reminder that our standard grant agreement for every grant, requires that all fliers brochure and posters and etc., with the prop k funding comply with the attribution requirements that requires to display the logo and we also discussed with sfmta and there in their sponsor ship of this event, we have made it clear to the bike coalition that our expectation is that the public investment will be recognized. >> so, moving on to the central committee neighbor way. this interest is for $155,000 in prop k funds for planning and out reach for the central richmond project that aims to calm the traffic and improve the bicycle connections to golden gate park, this builds on the earlier district one and the planning work. and in the san francisco bike
12:29 am
strategy. which identified 23rd avenue as a priority bike route. sfmta has revised the interest after conducting with commissioner fewer's office to include the investigation of the improvements on the parallel routes, such as 18th and 22nd. and this request is expected to result in final conceptual designs and environmental clearance by spring of 2018. and i can hand it over to my colleague, to talk about geary. >> mr. dental post. >> thank you. with the transportation authority. so this request is for about 600,000 to complete the environmental process for the geary bus rapid transit project. and the current status as a review is of course, as you know is just that the project, eir was certificated by the board back in january. and as part of that it was separated from the federal environmental process and the
12:30 am
environmental impact statement by agreement of the transit administration in order to expedite the process and we are working on that and that work is under way, and there was also a legal challenge which was stated earlier filed in february. and that was against the eir that was certificated in january. and so the additional pieces of scope that will be funded by this request are to complete the separate eis as part of that federal process and there is additional effort there as well as to incorporate the minor design changes, and so specifically for example, the 27th avenue, transition, where they transition from the center to the side and we heard the feedback from the community members and back in january, i committed that we would take another look at that desin, so there is additional environmental analysis and design work going on there and that is part of this request as well as finally responding to that challenge and pro-he vieding for the defense of the document.
12:31 am
>> that was just a quick refresher and this is the overview of the project that includes, the bus only lanes all the way from market street to the 34th avenue, along the corridor and it also includes the various other improvements with the up grades and the changes to stops. traffic signal, and priority improvements, and up grades, including new repaving, and street lights and light and other amenitieamenities. >> funding for the project total cost is $300 million and that includes about a little over, 200 million in funding from sources that have been identified and includes 100 million that we are seeking from a federal fta small starts grant. there is about, 91 million in sources still to be identified.
12:32 am
the positions the project well to compete for the various grant funded sources. and we have identified the sources for that 91 mill other than. >> finally the schedule looking forward, we have completed the eir but we are coming back with the eis and also the sfmta for we will need to take their sequa action to make their findings and we are expecting both of those things to happen by some time this summer. so will be happening. >> and with that, we can take any questions. thank you. >> are there any questions from commissioners for them as it relates to these prop k allocations. seeing none, are there any members of the public who would like to comment on this item.
12:33 am
seeing none, public comment is closed. and is there a motion to approve item 7? >> made by breed and seconded by sheehy and on item a roll call. >> same house same call? >> our house is the same. >> same house, same call. the action is item eight, allocate, 5 million, allocate $5,464,675 in prop k funds, with conditions, for the downtown extension including $4,549,675 for preliminary engineering and $915,000 for a tunneling options engineering study, and appropriate $200,000 for oversight of the downtown extension, subject to the attached fiscal year cash flow distribution schedules . >> so we heard about this at our last meeting, mr. cortiba is
12:34 am
available to answer any additional questions. i believe that mr. sabonya is here from the tjpa. both of you, a couple of few things, one is i think, the notion that we are all laboring under that this does not commit us necessarily to the street alignment, but that we areal locating this approximately, 5 and a half million dollars for do further work on the alignment. but it does not preinclude any action by this or any other body as relative to a different alignment that we want to go in understanding all of the cost implication, and the pros and cons for either alignment is that your understanding? the development of phase two
12:35 am
without impacting the rid study. once the rid stuffdy is complet later this year, we will be able to down to the sta and city and county of san francisco and to develop the strategies for bringing the train to the transit center as soon as possible. and then our trustee, commenter from the public, mr. lebron sent in an e-mail that i think that we are all in receipt of and that was also, forwarded by commission staff. relative to having a position at your agency. for a senior, and it is my understanding that indeed, you will be keeping a position opened for just that task in the future. >> yes. we are the only person currently working for the tjpa and so i need a little bit of help and once we move forward and i will give you to sfmta and the
12:36 am
department of public works as well to again, to share, to gain or to receive some of their expert adverti expert expertise, i have already talked to mr. fungi about stealing his knowledge. >> he told me that he is available for the threats. and then with regard to of what wi all have on cut and towsen. and mr. lebron suggesting some emerging technology, that might allow it to be forwarded. every option
12:40 am
>> these funds will allow for the cover work as well as updates to construction work estimate and rider ship and the ride of way costs. with the current turmoil in the federal transportation funding picture we need to keep the ball running, i urge you to approve these fund. >> thank you, next speaker please. >> good morning, share peskin, and vice chair tang and commissioners my name is bruce and i am the chair of the tjpacac and i am the member of the high speed rail and also central subway committee advisory groups, board members and transportation of the south beach neighborhood association.
12:42 am
thank you. >> thank you, sir, next speaker, please. i am with patrick and company in san francisco. and i grew up with the third and townsend connection and i moved to fourth and townsend, we need to get the train downtown, and the dtx is a critical element, and this board has dallieed for the last four months, not
12:43 am
approving these funds and that is no v in the critical path to accomplish this goal, i urge that this board take immediate action and approve this request to keep this project moving, we don't need any more delays and i have not heard you speak negatively, and so gets on the band wagon and get this thing approved. thank you. >> commissioners, i'm jim, and i am here to say, and i am here today to say, that what is before you is a big deal. and the public and the media may not understand it, but it is. the measures that you will approve today, or i want to say that the you know for the last five years, we have fusted around on how to get the train downtown, and we have not had a plan. and so what you have before you today, is finally a way to do that.
12:44 am
but that is only part of it, because the study is integral to that and if you approve the planning department's budget for the next fiscal year that will all be funded in a year from now we will have a coherent plan to get the train from the south side of the hill downtown. so, this is, this is something that you know, we have been fussing with for many, many years and it's now time to tidy it up. and important ingredient is that your ta staff with the money that has been allocated will have the ability and to make sure that all of the ability and the public agencies play nice, which certainly has not been true, in the past. and to accomplish this we will call out a couple of people -- and he is on a lot of committees
12:45 am
but he never lost sight of the bigger picture of how to get the train downtown, regardless of what is there, and the other is your staff and the director chang and who with the cloud of the money has managed to whip into shape, the various city departments and will continue to over see to make sure that we will have what we have been long, missing in that is the coherent plan to get the train downtown, thank you. >> thank you, mr. hess mr. speaker please? >> yeah, good afternoon, and the city supervisors, and i'm marvin and i am with the operating engineers, and we would like to you know, urge you to approve the tjpa prop k allocation interest request to extend the engineering and the design work for the downtown rail extension and the engineering and the
12:46 am
design work is focused on elements that are common due to all of the elements currently being considered in the rnb, reb study and therefore these funds will provide essential information to continue advancing this important project whatever the out come of the rib study is. and just for regular guy, construction worker that provide good union jobs for you know, local hire people and the people in the bay area, and so they can have a fighting chance to stay in the bay area, and with a, really help our apprenticeship, that will give the minorities and the people to start a career in construction, and let alone the infrastructure needs for downtown to alleviate some of the tra of course traffic, and so i think that it is a win-win win and i would like to urge you to help with the process here. >> thank you, sir. >> see no other members of the
12:47 am
public for public comment, public comment is closed. and before we have a motion, and a vote, let me just say particularly to mr. patrick a couple of things which is that i believe that this commission has taken this allocation which in the grand scheme of things is a drop in the bucket of what this downtown extension will ultimately cost. i think that we have taken it very seriously, particularly in light of the fact that with all due respect, phase one has been an absolute nightmare as it relates to cost over runs, and the delays, and no offense, mismanagement, and so, when we go into phase two, as i have said and i think that other members of this commission have said. we want to do it with our eyes wide open. we do not want to repeat but instead, we want to learn from all of the unfortunate things that happened in phase one.
12:48 am
and as a matter of time and delay, we are aware of the fact that the cal train electrication due to the actions or no inactions because of the city but because of the federal administration has been delayed and i don't think that this delay four months in approving would originally a $7 million request is now $5 and a half million, is not ultimately going to delay a downtown extension when it is properly built and with that, do we have a motion to approve item 8? >> made by vice chair tang, and seconded by commissioner kim. and on that item, same house same call. the allocation is finally approved. >> item nine. >> adopt the alemany interchange improvement study. this is an action item.
12:49 am
>> miss hyattishgs. >> not so much, i am standing in for her, i am jeff hudson the deputy director for planning here at the tran pourtation authority. i am here to present on the final report for the interchange improvement study that i trust will be coming up and. study proposes several changes to make it safer, and easier for people to navigate the maze. particularly on foot and by bike as well as to make the navigation, clearer for the people who are driving. and when we get a next slide up there, we will show you that this study was district 9's planning project.
12:50 am
go to the next. >> and this slide shows the neighborhood we are looking at. and the purpose is to improve safety and access for travel between the three residential neighborhoods that surround both the alemany maze and the farmer's market which is traversed by several high injury corridors it is an area that has several gaps in the biking network and the major safety issues for the pedestrians particularly because of an informal path that pedestrians have developed to or that have the crossing six lanes of high speed traffic without any signals or protection. in order to get to the farmer's
12:51 am
market and get there and back with the bags of zuchinnsxishgs what have you from the farmer's market. >> so in next slide shows the whole area. and it is kind of hard to see at this level. so i will refer to you, if you have the report in front of you it is on page 13, where you can see it more closely. and as you can see the maze is pretty well named, it is kind of complicated to go through that area. the upper graphic here shows the existing conditions and the lower graphic shows the recommended improvements and in the next few slides we will zoom in to see a few of those specific improvements. >> the next piece is the
12:52 am
intersection of san bruno, and eastbound and this is the proposed reconfiguration of that if you will click it again, you will go from the existing conditions to what the new configuration will look like. and it basically is it clears up a confusion about who is supposed to be where? right now, we have cars and bikes and pedestrians, all not entirely sure which part of the asphalt is theirs to use. and so we have conflicts that are dangerous and so we want to clear that up.
12:53 am
>> with several painted bulb outs that we think that will make a significant difference to that. >> and then the third piece to show, is the phase two of the project. and i will get to in describing the implementation, and this is the part that will formalize what is currently an informal path that pedestrians use to avoid a long route that they would have to travel if they followed if they follow the route that is currently prescribed. the path that is currently prescribed is one that would have the pedestrians cross five different cross the road in fieft different place and go two blocks out of their way from the intersection of san bruno and alameny and then another five enter sexes and two blocks out of the way to come back.
12:54 am
not a particularly safeway to go, but, people do it their recommendation there is to put in the new signal, two new sidewalks and a new traffic signal and two new crosswalks and a path across the area that median area. and that will be a little bit complicated because s it is an area that floods and we have to do the work to figure out how that works well and then the pedestrian scale lighting. to make it all safe. at all times of the day. >> finally, when we talk about the implementations strategies, and so phase one is what i described in the first few
12:55 am
specifics that is a relatively manageable cost and you can see that we have it estimated at 277,000 and have you already approved the funds to do this work through the end tip capitol funding program. sfmta the partners will be leading the design in construction for that and have that completed in 2018. and phase two is the more complicated part, and it has got a slightly higher cost, and still only over, two million dollars, and again, have you already funded the first step of that, which is a survey in preliminary design and then further steps will be led by sfdpw in coordination with mta, and cal trans, and that will take a little bit longer to get them. >> and i am happy to take any questions. >> any questions, and
12:56 am
commissioner? congratulations. >> thank you very much for all of the ta work on this. this was a top priority for the former commissioners. this one my number one priority for a number of reasons and colleagues i don't know if you have been at a pedestrian and a biker or a driver in the alameny maze it is a met. it is a confusing true maze two flee ways and five off-ramps and on-ramps and people walking across what is a freeway. on the ground. and when it rains, it is flooded everywhere, it is flooded under the freeways, it is flooded on alameny and two lines are completely blocked off on one
12:57 am
side of the street. and it needs to be a priority to fix for a number of reasons. number one it cuts my district in half and essentially makes it an island sxh divides it from vernal heights. and number two, as you mentioned it is incredibly unsafe. and i said, and i go to the farmer's market on most week ebdz and i live there and i do take the time to go out of the way to walk. cross right at a freeway off-ramp where there is actually a light. but what i watch is tons of people using that informal path which is basically running across five lane freeway to fwet to the farmer market on the other side. what i watch is senior after
12:58 am
senior, with their kashtsdz to the farm ir's market and i can't believe and i am knocking on wood here that there has not been more serious injuries and to me this is an equity issue. that the portula is a neighborhood that is working class low income neighborhood with a majority of chinese res that is literally surrounded by freeways, which way that you go. i am wondering why it is going to take until 2018 to complete phase one which we needed two or three years ago? >> so, do you have help on that?
12:59 am
>> thank you, our understanding is that it is the normal schedule for the agency to deliver to the phase one and we work to expedite that. the good news is that with the new funding deal there could be additional active transportation funds. so also, accelerate phase two. so our hope not to lose time and but to expedite them with the implement s agencies. >> it is really important to me that we get phase one done as soon as possible. and i would also love an estimate on phase two, which you expect that work to begin. >> we don't have a firm schedule we need to do the investigation with the cal transto understand the puc in this area. by this summer we should be able to provide you with a schedule. >> again i will be working with
1:00 am
you and be bringing this up constantly. because this is safety issue. and i want to expedite and if there is new sources of funding comeing in and imagine if we could make this project bigger than phase one and phase two. >> indeed. thank you. >> any other questions? >> commissioner? >> thank you, commissioner rohenn for taking the lead on this. i too want to ak co-a lot of the xhepts that were made here and a lot of the residents in my district traversed the same dangerous class ways and it is a lot of families and it is a lot of people taking their children on bikes.