accela system. we are in the final stretch. the last few months. so we are focusing on testing, training and outreach. it's literally building the computer infrastructure and installing the software on it. that's where we will do our next couple rounds of testing to make sure it works and functions as needed. literally the last couple days we wrapped up our first round of user acceptance testing, that's a positive thing and training has started. we started training on june 4th. what's coming up next month, training will continue, we will go into another cycle of user acceptance test. there's also a little bit of data migration and that type of activity that is also ongoing and should be wrapping up in the next month or so. you will see in color coding, the end of build, those dates were not met and there has been some impact on readiness. readiness is the testing and training. that's why you see the yellow for the current tasks. and i will talk about where we are under the risks and issues. the bottom line we did not make those dates at the end of