dan wade, and i'm pleased to report today on a response to the comments and recommendations, that basca gave us in the letter dated 2014 regarding the march 2014 revised water system improvement program. now just very quickly refresher on the revised march 2014 water system improvement program, compared to the march 2013 revised program is that the program was approved on april 22nd of this year, it includes a cost increase of $120 million and one month scheduled delay to may 2019. both of these overall changes are largely driven by the different conditions for the replacement project. as you know, as the end of -- so in review of the changes made in the march 2014 revised, basca presented mindings and recommendations regarding the budget, and schedule of the project. my goal today is to give you an overview of the response to these commons and actions that were taken to address these comments. so bosca divided their fundings and recommendations into three categories. the first set are based on budget and the second based on schedule and the third set based on scope of the projects. so