the abatement or spot of bateman had to be done in order to remove the seal. here is a picture of the demolition of the roof of the bus and deck and the outside walls. as of this morning, if you came by the private, they have completed about 2/3 of the removal all the way over to the west end. you can see daylight. they will continue taking walls down in this fashion with a nibble the top down so as not to spread the debris on our neighbors. it has actually been very well contained. no complaints. a couple of weekends ago on fremont street, they were taking the structure down, and that is what it looked like about two weeks ago with the entire removal of the roof deck and the walls. as i said before, to date, over 11,000 -- nearly 12,000 kraft hours have been completed. bay area labor has contributed 11,184 hours or about 94% of that labor. just taking a quick look at the time line, the events coming up through november by the weekend before thanksgiving, we will have the first street crossing completed. early november, and of this week or next, they will star