whether it was compressed and also address some of the questions raised by this commission as well as bawsca. carson did conclude that our construction and closeout schedule were compressed, but they did also find that our reports of systems and procedures are or should be adequate to deliver the program as is. they also pointed out that the fact that we have more projects completing in the last year of the program, there is going to be a higher potential for the overall completion of the program to be delayed past december 2015. they also pointed out that we will see a very significant increase in our spending over the next few years, which will test our ability to be able to address multiple issues. i'm confident that we will be able to task for the challenge because i think we've been able to do that up to this point. there was a second assessment conducted by an independent review panel made up of of your industry experts, and they focus their assessment on our program. this is the first of three reviews that this panel performs. in general, their findings were also very positive, and th