>> art jensen wiht bawsca -- with bawsca. we recommend that you approve the proposed schedule changes. we find them appropriate. we also recommend that the cost impacts continue to be included in subsequent reports to the commission. commissioner moran: any other public comment? seeing none, i have a motion and a second. all those in favor? opposed? motion carries. item 10. >> item 10, approve the selection of epc consultants in the seismic upgrade of a division pipelines three and four at hayward fault to provide various project-specific construction management services, authorize the general manager to negotiate and execute a professional services agreement for an amount not to exceed $8,500,000 and with iteration of three years and four months. >> if you want to call both items, they are related. >> item 11, approve the plans and specifications and award a contract to seismic upgrade of a division pipeline numbers three and a four at the hayward fault in the amount of 31,320,000 and for a contract duration of 825 consecuti