i'm bessey tammy director of wastewater capitol programs. today i will present the quarterly report for the wastewater program for q1 of 23/24 covered july first through september 30 of 2023. at the beginning of the fiscal year of upon 23/24 the city adopted the 24-33 capitol program. which is now used the basis for the project budget and schedule you will see in this report. here is the summary table that shows the budget and completion forecast adopted by the commission on february 14 of 24. so for the 3 programs we have a total of you see 120 projects the approved budget is shown with the compolice of 2037. we likes to start with construction updates. these other projects we want to highlight that are anticipating completion in calendar year 2024. on the last. area improve am projects, you see here that this is a photo showing the contractors paving between 14th avenue. most of the sewer work have been completed and we are already receiving benefits from the increase in the hydraulic capacity. now in the middle, is showing the contractors