. >> ed burkgar lopez. the cruise ship terminal project is a public works contract that is being managed directly by the port and staff. in may of this year we issued a request for qualifications for construction manager and general contractor services. the contract was awarded by the port commission in july of this year. that is one of the first major construction projects that included the 20% local requirements. we are in the pre-construction phase right now. in addition to the construction contract, i want to mention the design is being done by san francisco-based firms. and they also have a contract for all of that a and these services. they are working with sap on that as well they have doubled participation on that contract. it is up 45%, one of the highest on the construction side we have roughly $60 million. if we were to use a percentage of what we expect to go towards materials and supplies and labor, we would estimate in this contract 60% of those $60 million would go towards labor. that is 24 m