. >> the contract and mechanism is c.m. g.c., and it standards for construction manager and general contractor. we do a six step process, where we go through r.f.q., mean a qualification, to really perfect the phasing logistics. so we've gone through the r.f.q., where we have short listed four contractors. so the next phase after that is to do a request for proposal. that is based on both a cost criteria and a non-cost criteria. and that's currently targeted to be issued in the next month or so with a goal to have a contractor selected by the end of the year. and then have ntp for this contract by the early part of 2020. >> so you're looking for one general contractor to manage five projects, or multiple general contractors? >> so we are looking for one general contractor. and how we would deliver the projects would be the general contractor would be responsible for doing what we call the packages or trade pac packages, and we would pre-qualify general contractors, and they would do the same thing to qualify contractors. and th