on a 2013 design. the best available information i had to inform the 2018 baseline was at a 35% level. similarly, here's the 65% cost estimate. remember, this is where the cmgc first came on board. next, now, this is our original 95% cost estimate with the cmgc inputs that we talked about, and it had a project cost of 2.3 billion with a duration of nine years. and lastly, and lastly, here's our reduced 95% cost estimate, with the $550 million reduction from the original 95% cost, the construction cost is now $1.2 billion, bringing the overall project costs to $1.68 billion with the construction duration of 7.8 years. >> is that a firm number of years? >> no. we are -- the cmgc is still finalizing the construction schedule and incorporating all the changes we made as a part of the scope reduction, so, you know, we're hoping there's still some fine-tuning of it, but it is probably -- >> yeah, i was going to jump in at this point and say the cost and schedule numbers that you see at the bottom right are currently the best estimate that we know today considering the efforts that it took us to get to this point, reacting to the shock last year. under traditional design bid build we