. >> good afternoon, commissioners, dan wade and today's report covers from october 1st to december 31st of last year. at the end of the reporting period, the regional program was approximately 86 percent of the local program approximately 99 percent in the overall wsip complete. the overall program continues to be on schedule and on budget. that is that all of the projects will be complete by 2016 except for threee regional projects. those projects will be complete in construction by the end of 2018 and the total program would be closed out by 2019. our major activity obviously continues to be in construction. we have 14 projects in active construction worth about 2 1/2 billion dollars and as you can see from this chart, we only have two projects remaining in preconstruction, namely the alameda creek recapture and the ground water storage and recovery which is soon to go to construction and we have completed construction on 65 projects worth about a billion dollars or actually 1.3 billion. now, as always we have a number of accomplishments to report. rather than read off of these off to