first of july of this year, the executive operation of the gas transmission line was started from dashtak in sistan baluchistan to nahundan, so that south khorasan is connected to the transmission line in the southeast of the country. now, after 6 months have passed since the beginning of this project, we went back to its implementation site. 176 km line. and at the same time as the construction of the road , it has been about 50 days since the laying of pipes has started . so far, 60 kilometers of the road have been laid , testing, channeling, welding and all other pipe work. after the opening of this stage in the first 3 months of next year, the second stage of this project will be started from nahundan to sarbisheh. seyyed mohammad reza hosseini , nahondan radio and television news agency. in the past week, the main indexer of glass hall has recorded a negative return of 1.14% in its portfolio. however, experts believe. the price correction that happened is not alarming. the main indicator of the stock market is the resistance range of 2 million 200 thousand units in the first week. we