that moves us to the bureau of fire prevention investigation update from fire marshal dicosio. on page 21, total permit inspections completed in october was a whopping 639, and the port, 113. another point i'd like to make is at the bottom of page 22, r-1, r-2 inspections. they're buildings below 75 feet, and buildings with more than two dwelling units. most of those inspections are done at the company level, so engines and trucks do them. the corridor between engines 4 and 3, and engine 36 are some of our busiest companies, so those companies that are going on calls during the day have to try to knock out five inspections during the day. it's very labor intensive, so fire marshal dicosio has knocked out a great program to try to takeoff the load of some of the inspectors in that area. so in october, you can see they did 72 inspections to help take the load off suppression, and that's been a fantastic program. also, the batallion chief monthly meetings have still been beneficial, so thank you, marshal dicosio. the community outreach, they had 15 community presentations, and the