my name is eric thrasher. i am with -- >> supervisor fewer: hi, mr. thrasher. >> i am with san francisco department of public works, bureau of street use and mapping. i have been liaisoning with our partners at telemon engineering study, the master plan underground utility study. i'm going to invite doug zeiring with telemon to discuss the slides. this isn't the actual study. we're giving you a sneak peek. the results should be completed sometime late august or early september. just quickly as a way of background, the last program to underground utilities in san francisco began in 1996, and from 1996 to about 2006 roughly 46 miles of overhead wires were undergrounded in the city. at cost of about $173 million. as was mentioned earlier, the 20(a) fund that was used to pay for this program went into deficit and that's why the program stopped in 2006. there is currently a program, a second streetscape program underway which will involve two blocks of lines that will be undergrounded, but aside from that nothing has happened since 2006. i would also mentio