it's got a large gta, 2-1/2 acre park plaza and a tip at the end. so, it's quite a large facility. we already talked about the design services. in terms of the budget for the project, it was phase 1 cost $66.31 million. total project is estimated to cost 112 million, but we added a 2 million dollar contingency to manage project risk in the budget analyst report. this slide shows phase 1 ask title 1 and 2 project costs [speaker not understood]. the budget analyst report notes that we have all the appropriations for the project, but 23.78 million. the supplemental before you would make that final appropriation. other sources for the project are varied and it's been great for the port to have support in building this project. we have 58% port sources, 16% a passenger facility charge. we've done some work on how much we can charge, reasonably charge our passengers to help us repay the cost of this facility. with the help of san francisco voters in the last clean and save parks bond, 15% of the project supports those park and open spaces. we have a city contribution of 5% and a fema gra