this photograph was taken at the bear gulch site. work has already been completed. construction activity is 24% complete. i recently attended a few construction meetings to verify everything was on track and i'm pleased to report no major issues so far that would require management involvement. the work now is focusing on the massive excavation and the wall that will be needed to build the 11 million gallon reservoir. we are proceeding with the demolition of the sedimentation basin as we speak. as of mid october, work on crystal springs number to in south san francisco was completed and was successfully put back in service. we're beginning work in hillsboro, adjacent to some very affluent areas and sensitive creek habitats. to deal with doing work in such busy urban area, we're being very proactive with our public outreach by involving all impacted businesses, homeowners as well as city staff, keeping them up to date on our activities. the project has its own twitter account and blog which receives a lot of traffic and it is a great way to communicate. construction