haa ha ha! ha hha ha! [snortg] please stand by. please stand by. please stand by. so 03 executive directors report. >> since our last meeting on october 14, we continue to make progress. an excavation package is ongoing. how the court pallia architect is 20% complete with the documents. the request for qualification for the design build construction services trade package was advertised october 4. we received responses to the rfq. we have a value in the responses and will be sending out a notification next week. we have also issued a notice to proceed for the utility relocation contract. the first reconstruction meeting was held on october 21. with respect to the second and third utility relocation visits, we expect to issue those on november 9 with the fourth one being issued november 6. at the terminal we are expected to complete phase two of the terminal for operations to commence around december 11. i did want to mention with respect to rider request on the benches, we have increased this about 15%. we have all so requested five more benches with armrests for p