being now 98% complete of the slope plant, before long we will only have remaining work at the harry tracy water treatment plant. construction has been completed on four of our six storage projects, as indicated here, the calaveras dam project is now 39% complete. ~ the regional groundwater storage project is one of the three projects remaining in pre-construction and it is now in the later stage of design and environmental review. [speaker not understood] progress has also been made on all our transmission projects as indicated by the amount of blue on this slide. all these completed projects have already added significant delivery to the seismic and delivery reliability of our system. five transmission projects with significant seismic delivery reliability -- seismic reliability objectives remain, and you can see here on this slide our two ongoing tunnel projects are the only two remaining segments needed to complete the new life line being built around the bay. and the new tunnel there is 79% complete, while the bay tunnel is slightly further ahead at 81% complete. so, shown here is a h