this is the jamie carpenter art display. the concrete was poured. this rectangles in the floor are light features. the benches are light features, all part of jamie carpenter's concept, and now the concrete is secure, and in about amount -- a month, all the lights will be up it will be sealed and will be completed. traffic signals. this is the challenge we've had with getting those activated. pg and e., my bullet in the upper right says may 21st. they just informed me last night that they will have their parts until may 24th. but at least it only slipped three days, so that was the way i looked at it, but m.t.a. is queued up as soon as pg and he finishes their work so they can fire up those signals to get the crosswalks straight, get the signal timing and all the pushbuttons all activated. m.t.a. is anticipating in the winds, waiting for pg and eat to finish their work, then we can get the three crosswalks on first street going and remove all the public works barricades which are all along the first street barricades at this point. ceiling panels ha