scott, and i'm here to discuss the jerry garcia amphitheater and possible amendment. this is discussion and possible action to amend the construction contract with angotti and reilly,, inc. , for the jerry garcia amphitheater improvement project, to increase the contract amount by up to $225,000, bringing the revised not to exceed contract time to $791,369. this project is funded by the citywide project for the john mclaren park from the 2021 clean and safe parks bond and also the safe bond -- 2012 park forestry funding. the scope of the renovation work is expanding the paved flat areas to allow for food trucks and other amenities for larger events to take place as well as expanding a retaining wall and regrading for improved drainage, and we're also improving the access road that is unpaved that will reach the back of the amphitheater. so this project was not brought to the commission for award of contract initially as it was under the $700,000 threshold for a formal contract, so that's why this is the first time you're hearing about this contract. however, the commi