joe chen, public works program manager. i would be providing updates on the upcoming milestone, the activities on the zuckerberg building five component as well as the community health center component. so let's focus first on slide number 10, that will be on zuckerberg building five. we are currently tracking two projects in construction. this is well into construction. contract had some -- had a slow start to get all their infection control submittals in place but we are into demolation that will continue for the next month or two with our target date to finish is towards the end of the year. another project we just launched is the rehabilitation department relocation, recreate for construction was granted yesterday. we've been working closely with the contractor to get all their subm submittals in place to give us a good head start. we are currently tracking to start construction. we'll hopefully get abatement controls, procedures approved and have construction start in july, end of july is what we are targeting. that pr