joey labonte. i'm glad todd had some good news because mine may not be quite as got unfortunately. this is the quarterly up date for july august and september. the updates include the latest forecast on the significant changes associated with the calaveras project. and the second half of my presentation will focus on those changes. as of the end of september, the resip was 68% complete over all. and as with the past several quarters, most of our focus has been on construction activities as shown on the chart here. only one of the three projects that still remain in design at this point are seismic reliability projects. the good news here is that all seismic reliability projects are either in construction or have been completed. so the large changes on the calaveras replacement project are reflengd here in the regional program variances reported for this quarter. we -- if we focus on the numbers for the regional program, you'll see that we are now forecasting the cost of regional projects to be 150.6 million more than the total budget approved for these projects and this will presen