. >> my next item is julie labonte, -- update. >> good afternoon commissioners, my remarks will be brief. i think your packet includes a copy of our latest quarterly report and i wanted to point out the fact that that report includes the latest budget and schedule, revised, did you approved in late april. also the report includes some format changes at the front to address in particular one of the recommendations by bosco related to project contingencies. we now have a more detailed accounting of the contingency remaining in our program. finally, i also wanted you to know that we are currently working on two documents, a change notice report to the state that will be completed by the end of june; the report will highlight the impacts on -- goals that the project delays will have. i want to reiterate that those los goals have been changed, achieving full reliability according to those goals has been delayed because of our project delay and that will be documented. there is also a memo forthcoming to the commission that will address some of the recommendations that bosco have put forth ear