so as part of my general manager report, i wanted to have julie labonte come up and talk about the wsip update. >> good afternoon commissioners. first i would like to begin by telling you about two important milestones that were reached earlier this month. on the new irvington tunnel we holed through on our second and last segment of the tunnel. so this was definitely a majority achievement. i think over the past few years you have heard about how challenging the ground conditions were and the safety risks associated with that work. so we were obviously extremely pleased when the crews from the two sides of the tunnel met finally, i think it was two weeks ago specifically. so obviously the risks of that project will be going down quite significantly. also earlier this month on the bay tunnel, we completed the installation of the pipeline lining that goes inside the tunnel. that is a 108" welded steel pipe that has all been installed and welded. so again, so we're filling the space with a foam concrete. i'm not sure if some of you heard or saw some of the good, positive press we got on t