we remain committed to a two site strategy at los alamos, two site pit production in los alamos and the riverside with los alamos having the capacity to produce at least 30 pits per year in savannah river -- and savannah river able to produce 50 per year. we anticipate los alamos retaining the capability to produce 30 pits per year with increased manufacturing rate confidence as we install equipment through 2030. at savannah river, we are focused on completing construction of the savannah river plutonium processing facility in 2032. once construction is complete, we will need to introduce nuclear material, established a manufacturing process, achieve fpu and then obtain rate reduction by about 2036. that's not all. nnsa made significant progress on the infrastructure at both sites to promote pit production. srppf, establishing the machining center, teaching critical skills and develop -- develop competency for training. at los alamos, 80,000 square feet of warehouses were completed to provide controlled storage and areas for equipment, practice for radiological work and testing of glove