. >> good morning, directors, martha valez, facility manager. the link intended improvements with the focus being the amtrak and greyhound space. first is the contractor selection as we noted last month, an r.f.p. was done with three rerespondents, and lincoln is finalizing the contract with turner with a recommendation and contract approval to come to the tjpa this november. this does make the schedule tight at this point. however, lincoln is still on track for completion of the initial greyhound amtrak t.i.s in march as noted below in the work stream. with regard to the design, architect is on board, focus greyhound and amtrak, and as of today construction drawings are a week to ten days away. this is the facility maintenance on the facility services contract. on track for the r.f.p.s to be completed by the end of the calendar year. commissioning and training dependent on web core. they are having regular meetings and some initial training has already started with the chief engineer being trained on fall protection. the rooftop park, just goin