maxine hall is -- has already completed design. we're in the d.b.i. plan review, and we also anticipate starting construction first quarter 2019. there is one potential risk impact. we're working closely with d.p.h. and staff to identify some possible location to see relocate the clinical and administrative staff been -- within the building. there's been a lot of concern about staff from noise, impact, so that's one thing we're working closely with staff and their public relations person to really flush that out at this point. castro mission is not too far behind. we are anticipating finishing design by the end of the year and probably starting construction in the second quarter of 2019. on the ambulance deployment facility, this is one of the fire department projects, we have completed our design permitting, as i mentioned earlier. bidding started in june. we actually received bids last week. we did get two bidst