we had one permit approved for maxine hall. actually, it's for -- yes, it's for maxine hall, we issued notice to proceed. i think mark alluded to the contract, the uptick in the budget because we awarded that contract. and that's what i have for accomplishments for both ambulatory care and zuckerberg. i'll pass this on to joe to talk about milestones in the future. >> thank you, terry. good afternoon, commissioners. joe chin, san francisco public works program manager for the 2016 health and safety bond program. i'll focus on two topics. upcoming milestones activities, as well as the overall view of the program schedule. let me first go through the upcoming activities. overall, on the building, five components, we are tracking 19 core projects and of the 19, we're working on 15 of them. so when they say 15, the projects are in various phases of the life cycle. either completed or in construction or in the early phase of program design. with that said, let me give you an overview of some of the construction projects in construct