the water on minna, utility relocation. the freemont water relocation outside of 301 mission. just to give you an idea, some of the coordination we had to go through. this is first street. this was during the holiday moratorium, so there was a lot of successful work that got done in that period. the demo contractor, 27,000 hours. of that, 97% had been filled by local labor. we are starting to begin work with these helicopters -- the subcontractors. the next big thing that you will see if you come by the site next week is a crushing operation near mission street outside of our offices. that will start to supply ballast material. we project by early march, late february, we will be down to the ground and into the basement of all the buildings. so we are pretty close on track, allowing some of the issues we had with abatement work we addressed earlier. utility time line. those packages were released last month by the board and they are getting started this month. that is it for me, unless i can answer any questions. >> great. now that concludes my report. director ford: thank you