just some shots of natoma coming down. it ended up being more of a thick-frame building then we envision, but it came down rather easily in about four or five days, and they have been removing the debris pile for the past few days, and there is a one-story concrete deck they have been working on. shaping the piece is for the hawkins and artworks -- shaping the pieces for the hawkinson artwork. the utility location continues to work. these are some of the tougher areas they continue to work this past month. that is beale and howard and the effort that goes into that. the work under second street at the end up -- of natoma. as i said, ministry repairs were completed this last june. there is a picture of the screen wall that was finished. as far as the bay area labor, we are still at over 80% coming from the bay area on the 52,000 hours that evans brothers has completed. about the same -- 84% on the 31,000 hours completed thus far by the trade contractors working for webcor/obayashi. this is where i want to move into a little