right underneath on natoma, this is where the food trucks are. that skin that covers up where the structural girters are for the bus ramp, that got completed. so all those projects that we were tracking were done, and ron will talk to you about that in the next few slides. thank you. >> good morning, directors. thanks, dennis, we're true low buttoning -- truly buttoning up and closing things up and winding out of phase one so mark can have full focus on phase two and operations and i can return to my day job. the trade group status is coming right along. in fact, we've got 14 subcontractors out of 47 done and gone. we've got 20 that are all but done, whether it's a signature away or the last throes of discussions, but that would be what's shown in the blue and the green on the graphic, so we're winding up very nicely. that leaves us with 13 subcontractors with webcor that are going to be going through the -- some sort of dispute resolution process, whether it be a d.r.a., continued discussions and negotiations or lawsuits of last resort. but we'r