the lot between fremont and beale will be turned over to the webcor/obayashi team. we have moved the crushing operation three times now from the east end to the central. that is now processing material to be recycled and used for the back fell at the west end of the project. regarding the utility relocation package, work continues on natoma with sewer and water. beale street and howard work continues. waterworks and sewer work on natoma continues. that just began. the 4.51, the first relocation package, the joint trench work on mena is continuing. 4.6, one of the final packages, is before you today for approval. the 301 mission wall is temporarily under way. we have put up a temporary screen in front of it so the work can continue. we have demolished the original so we can complete work in the eastern lot. that is well underway. finally, the transit center and individual operations starting their. we have a buttress shoring and excavation package that was approved earlier this year. there permits are in place. -- their permits are in place. they plan to mobilize on