north point outfall system rehab. the contractor is continuing with removal of sediment, interior cleaning and apoxy lining and this is a picture of our senior environmental engineer and she is standing in the freshly lined outfall. this is kind of cool. it is a at 60% completion. client construction on our green infrastructure. chinatown is progressing. it has been a very challenging project. many things were exposed during excavation of that project. we're looking now at a completion in march. we will be sealing it all back up so it is in tack for chinese new year. so, february will be good and safe and then we'll look to wrap that up in march. the wiggle demolition has commenced. if you've been down on heat street, that is starting to look really nice with the repaving. that project is at 60% completion. visitation valley, that is a project with rec park. that is moving along really well. the contractor just installed rebar and forms and we have our first rain garden put together. that project is at 49% and the tea