this is scott zacker. he's the guy that took it down, essentially his company and they did an amazing project. i never have seen a demolition project like this and huge cracking jobs. they did it from working on the deck and pulling this up and we expected to be a six month project and it happened in three and helped with the schedule. he's a happy man. we have the construction company come in and start driving piles in july. this is some of the equipment. it was all done from the water and all right along the embarcadero promenade so you see we have steel piles and concrete piles. that's a $20,000 pile, concrete pile or the steel pile and this is a concrete pile and 260 piles in total -- i don't know how that got in there. a little bit out of order. back to demolition. some more pile driving. the crew just had a great time out there. it's spectacular place to be. they're right there. we had no accidents at all and you can see it happening there and the america's cup was happening and pier 30/32 and the bo