the cast nodes as dennis were delivered to skanska. the barrettes were tested and passed with flying colors. no anomalis in the barrette pilots piles. shimmick choose to use a different subcontractor and were live clean bill of health you will start to see the pylon itself start to get constructed. looking forward this month and the next couple of months, i think i pointed most of this out -- the big goal is just to keep moving the lower concourse decking to the east from about where it is at fremont street and more form work and moving that alone. of course to do that, the walls below have to be completed of the structural steel erection is continuing and they have to do the timing between disassembling the trestleand moving into more erection areas. the next big obstruck obstacle will be crossing the street. in march and april start the steel erection that will complete the west end from 10 line towards 1 line and back off the trestle to howard street and be gone. we'll see that start in march-april of this year. great participation