. >> the next item up is 525 golden gate update by sophie campbell. >> good afternoon. i am the project manager for our new headquarters at but hundred 25 golden gate. i want to give you an update on the project and to review of the project budget. i will wait until the slide comes up. all right. hopefully, most of you have noticed the project going up next door, adjacent to the court house. we are now above our adjacent neighbor. we added a seventh story this week. according to the construction schedule, we are at about 25% completion. as the building rises, you gain economies and are able to shave days off the schedule, but with the weather our concrete has been very temperamental. one of the sustainability stories of this project is the very high some of replacement in our concrete mix -- the very high amount of replacement in our concrete mix, a 75% ash and other materials. we are going to top of the building in april. then we will begin installation of the curtain wall system, the exterior glass and stone skin of the building. that will be completed in september. b