on top of that as noted by steve roll scasta is doing a whole schedule they're adding multiple shifts that's why we're adding a 6th facility that includes additional inspectors that projected to be $20 million for the quality element of the project. second bullet has to do with the cmo and additional scopes that have been added over the entire life this is projected through 2018 as well. our holding schedule second and third shifts have been utilized by the contractor that was not in the original scope as well. so it's prudent to have one set of eyes from turner out there from the second shift one set of eyes for the third shift that's what we have for each one of those and also the claims assistance and change orders adds up to the 7 million that is over the entire life of the contract through 2018 is projected then the last $12 million is compellation of our waterproofing inspection we anticipate for the water rooftop park sgh we want to ensure we have good waterproof product up there and the project and partnering there is 10 to 12 mislanous items adding to $2 million that's the ba