steve ruhle, with turner construction. just a couple of highlights. we have over 200,000 hours going without major incident or within the transit center construction. our executive director mentioned 55,000 hours. now we are into the transit centers that have over 200,000 hours without incident. some of the highlights of the last 30-45 days, up retrenching has been completed, as has the cdsm wall. this is the graphic i used before to show you where it was in progress or were the pre- tragic was in progress. you will notice there is only one color. there are four gaps remaining. half ofe street still needs to be crossed when -- one of the final utility areas are finished. that will be done and the first half of next year. there is a scene in somzone four where we're doing work. they are planning to for the 27 tomorrow. the weekly average from the time we started in early september is just over two as a production rate. we want to get that up to 2.5. those yellow circles were the ones that were completed this week. i put the slide together last week. th