we had the e.n.a. to discuss and the few that are remaining to be achieved and we indicated that in true compliance with the e.n.a. and indicated that the development costs have increased to $135 million. and we indicated that the e.n.a. has extend ed the authorization provided on the e.n.a. will expire on november 4, unless there's a request for extension. as indicated on this slide, this is showing the benchmarks that developed to date. on the e.n.a., as i indicated, it's a one-year term. the reason it's taken this long, many of this was achieved back in 2016, was the entitlement process and a number of development tasks that need to be completed. given the nature of the site and given its location in a unique, urban setting. the embarcadero promenade, waterfront district and gateway location, it took a while to get a consensus on what we call project description, win is the basis of what needs to be done. they're making progress, but all the issues have taken longer than anticipated. that was the rea