the m.o.u. between d.p.w. and the branch library improvement program helped a lot. there were a lot of, i think project management is actually an issue with some of these bonds and that when they actually do some memorandum of understanding then things do seem to get better. and this was probably the most similar the other bond that we have out there that's similar to this in the sense there's lots of little projects is the park. so that's one we can hopefully learn from the branch library project. and here we are, there was a $2,000 bond and then a 2008 bond. the 2000 bond was for $10 million and the 2008 with for $185 million. 2000 did have its difficulties. there was a lot of change orders that occurred. we are hoping, and obviously not at the end of the 2008 bond for completion, but we're hoping that the m.o.u. again between d.p.w. and recken park is going to help with those change orders. nonetheless, and this is a concern to us on the board right now, on the commission is that the committee is that there are delays already. some of those delays are greater tha