fatalities for contract to, the worker run union square. a little around 25% complete. the total contract is the next one. this contract is broken up into three parts. the notice to proceed one, the tunnel boring machine procurement, the access pit. those two are part of this allocation request. then there is notice to proceed 3, running up tunnels. that will not take place until the full funding agreement from the federal government is received. the bids were opened from this contract on june 8. $13 million below the engineer's estimate. mta plans to give notice to proceed to the contractor in september. the early construction is fully funded with $72.7 million in prop k, the rest and prop1b new starts. the staff recommendation is the allocation of up to $57 million with conditions. those conditions are upon contract award, and a surplus prop k funds will be the obligated. these funds will then be used for other phases of the project. another special condition is, should any additional funding becomes available, federal funding, state funding, or funding that can be app