we are predicting an underrun of 1.1 million over what was approved. the completion date is the same as what was approved by the commission. this is a chart comparing the total forecasted program in blue to the total program approved budget in red. the approved budget, the red line includes the program management reserve for the forecast does not. he essentially, the delta between those two lines are the program management reserves. we are tracking well below the budget approved by the commission still. the overall program costs since the last quarter went up $14 million, due to the initial construction contingency approved by the commission for the datavision pipeline approved at the last commission meeting. for the first time, i wanted to show you a report on the transaction in and out of the program reserves. the numbers on the last column in red are the monies moved out of the reserve since the program was approved in july. on the left side are the savings moved into the reserve. since the program was adopted, the commission approved an increase in